TeraWulf Moves to Vertical Construction at Anthropic-Leased Kentucky Site

Steel for the first two buildings is on site at TeraWulf's 480MW Hawesville campus, where Anthropic will lease capacity with Google as backstop and Fluor handling construction.

3 min read

TeraWulf starts construction at Kentucky data center campusNetworks & Infrastructure
TeraWulf starts construction at Kentucky data center campusDoğan Alpaslan DEMİR / unsplash

Why it matters

  • TeraWulf's 480MW Justified Data Campus in Hawesville, Kentucky has begun vertical construction, with first facility due online in 2027.
  • Anthropic will lease capacity at the site, with Google acting as a backstop.
  • Fluor Corporation is the EPC partner; structural steel for CB-1 is mostly delivered and CB-2 deliveries are underway.
  • The 790-acre site was a Century Aluminum plant that operated from 1969 to 2022.
  • TeraWulf operates a Buffalo-area campus with Core42 and Fluidstack as live customers.

The story

Steel columns are now standing at TeraWulf's 480MW Justified Data Campus in Hawesville, Kentucky, marking the project's shift from foundational work to vertical construction ahead of a planned 2027 opening for its first facility.

"First structural steel is going up at our Justified Data Campus in Hawesville," the US data center firm said on LinkedIn this week. "The majority of structural steel for CB-1 has also been delivered and staged, alongside substantial deliveries for CB-2. This marks an important transition from foundational work to vertical construction as we advance the development of large-scale infrastructure, purpose-built for our customer Anthropic."

The steel deliveries cover the first two building phases, CB-1 and CB-2, at a site TeraWulf announced only in February. Construction timelines at hyperscale campuses routinely slip; roughly five months from announcement to vertical build is a fast pace, but the 2027 service date still leaves room for supply-chain or power interconnection delays that TeraWulf's statement does not address.

Who is leasing the capacity?

AI developer Anthropic has agreed to lease capacity at the campus, with Google acting as a backstop on the deal. That structure gives TeraWulf revenue security should Anthropic's requirements change, though neither the lease terms nor the backstop's duration appear in the company's disclosure.

The campus occupies a 790-acre site in Hancock County that TeraWulf acquired from Century Aluminum, which operated an aluminum processing plant there from 1969 until 2022. Repurposing former industrial land is a pattern across the sector: heavy-industry sites arrive with existing power infrastructure and grid connections, the scarcest asset in data center development today.

Who is building it?

Engineering, procurement and construction work sits with Fluor Corporation. Leo Kaid, president of Fluor's advanced technologies & life sciences business line, addressed the project earlier this month.

"Fluor is proud to expand our partnership with TeraWulf and support the delivery of infrastructure needed to meet the rapidly growing demand for artificial intelligence and high-performance computing," Kaid said. "Our integrated engineering, procurement and construction capabilities, combined with our data center expertise and skilled workforce, position us to deliver this important project with a strong focus on safety, quality and schedule certainty."

That is contractor language, and it commits to nothing measurable. The concrete deliverables — steel staged for CB-1, substantial deliveries for CB-2 — come from TeraWulf itself.

How does Kentucky fit TeraWulf's portfolio?

TeraWulf already operates a campus outside Buffalo, New York, on a 180-acre former coal power plant site. The company initially mined cryptocurrency there before pivoting the facility toward AI and high-performance computing workloads. Core42 and Fluidstack are live customers at that site, giving TeraWulf operating revenue while Kentucky comes online.

The company is also developing sites in Maryland and in a second Kentucky location, and it is planning an additional development in Lansing, New York. The Hawesville project is the largest disclosed so far at 480MW.

Beyond CB-1's 2027 due date, TeraWulf has published no phased capacity schedule for the remaining buildings, no total investment figure for the campus, and no timeline for when the full 480MW will be energized. The pace of steel delivery suggests the first building stays on schedule; everything after that remains a stated intention rather than a commitment.

Also reported

Share this article:

« PreviousNext »

More from Rebecca Stone

Rebecca Stone

Show full bio

Correspondent covering technology and product news in Carrier business, 5G and 6G, fiber and broadband at Telecom Gazette.

580 articles