Fermi lands 600MW hyperscaler deal as TensorWave lease dies
Fermi signed a 600MW power deal with an unnamed hyperscaler committing $200m upfront — while confirming its 650MW TensorWave lease and AMD credit deal are terminated.
Telecom BusinessWhy it matters
- Fermi signed a 600MW power deal with an unnamed hyperscaler at Project Matador, Texas, with $200m upfront and power starting next year
- The TensorWave lease for up to 650MW and its AMD credit support agreement are officially terminated
- Fermi reported a $141.6m net loss for Q3 and debt of $958.4m; shares sit at $2.15 versus a $30 IPO price
- A further $15m site development agreement is signed and a $90m materials purchase agreement is being finalized
- Project Matador could reach 17GW but Fermi remains pre-revenue and without a signed tenant
The story
Fermi has signed a 600MW power development deal with an unnamed investment-grade hyperscaler at its planned Project Matador campus in Texas — on the same day it confirmed the termination of its only tenant agreement, a lease with AI cloud operator TensorWave for up to 650MW that had been underwritten by chipmaker AMD.
The hyperscaler has not signed a lease. It is, however, putting money down. The customer will provide $200 million upfront to bring power capacity online beginning next year, plus $15 million under an early construction and site development agreement. The two companies are also finalizing a $90 million structural steel and building materials purchase agreement, which would let the customer draw on long-lead materials Fermi secured in advance.
Fermi said the client "is making financial and development commitments ahead of finalizing a lease, reflecting the importance of securing access to power within its targeted delivery timeline." Translation: the money is real, the tenancy is not yet.
"Hyperscalers want sites that are ready with permitted power, and Fermi's Project Matador is one of the few that can meet that demand today," said Lee McIntire, Fermi's CEO. "Our head start in speed to power is a key reason an investment-grade hyperscaler has signed up for 600MW and committed more than $200 million up front to accelerate construction at Project Matador, with an additional $90 million contemplated."
What does the deal actually commit to?
Three funding instruments, one of them still being negotiated. The $200 million covers power delivery from next year. The $15 million site development agreement, in Fermi's words, "establishes a framework for advancing site preparation and construction activities as soon as possible to maintain the customer's desired schedule." The $90 million materials agreement remains at the "contemplated" stage.
McIntire framed the deal as the first of many. "If we successfully turn this pipeline of prospective customers into leases, it would completely fill our 2.2GW of current capacity," he said, adding that the company could "evolve from pre-revenue, pre-lease to the next phase of growth." That is a conditional statement about a pipeline Fermi has not named, priced or timed.
What happened to TensorWave?
Thursday's statement was blunt: "Fermi and TensorWave have terminated the data center lease and services agreement signed in August 2026. The AMD credit support agreement associated with TensorWave is also terminated." Earlier this month, the deadline for closing that deal — worth up to 650MW of space — had been missed. At the time, McIntire insisted both parties "remain committed to this lease" and were "continuing to work through the remaining conditions prior to close." That commitment lasted less than a fortnight.
Fermi is now, once again, without a signed tenant.
A short history of deals that fell through
The pattern predates TensorWave. In December 2025, a proposed tenant pulled out of a $150 million lease on Project Matador, crashing the stock. Business Insider reported — citing Fermi's then-CEO Toby Neugebauer — that the tenant was Amazon, and that the deal would have paid Fermi more than $20 billion over 20 years. Fermi denied Amazon was the tenant.
The governance record is similarly turbulent. Fermi was founded in January 2025 by former Texas governor and energy secretary Rick Perry and Toby Neugebauer. It went public that October at a $15 billion valuation without any live IT capacity. In April, Neugebauer and then-CFO Miles Everson departed; Neugebauer, still the largest shareholder, has since repeatedly attempted to regain control, trading press-release insults with the company. His ally-turned-opponent Griffin Perry — Rick Perry's son, Fermi's second-largest shareholder through Caddis Capital — accused Neugebauer in May of trying to "seize control of the company in pursuit of a hasty and ill-advised sale." Rick Perry was not reelected to the board last month, with Neugebauer voting against him.
What the numbers say
Fermi's quarterly results, released the same day, show a $141.6 million net loss for the three months to the end of September, with debt climbing sharply to $958.4 million. The share price, which hit a low of $1.55 earlier this month, rallied to $2.15 on the hyperscaler news — still under 8% of its $30 IPO price.
Project Matador, a potential 17GW data center and energy campus near Amarillo on Texas Tech University System land, remains exactly that: potential. Fermi says power at the site will start coming online next year under the new agreement; whether that deadline survives where the TensorWave and 2025 leases did not will be the test of McIntire's conversion pitch.