Nscale Doubles Active GPUs to 50,000 as It Chases 461,000 Target

Nscale's updated IPO filing shows 50,000 active GPUs, 1.37GW of capacity and a $105.8bn contract book — but no financing yet for its $45bn Anthropic deal.

3 min read

Nscale brings online two data centers and 25,000 GPUs in 2.5 monthsNetworks & Infrastructure
Nscale brings online two data centers and 25,000 GPUs in 2.5 monthsAI-generated

Why it matters

  • Nscale doubled active GPUs from 25,000 to 50,000 between August 31 and mid-November 2026, against a 461,000 target.
  • Active data center sites rose from five to seven, with ten more in the pipeline and 1.37GW of active and contracted power.
  • Contracted TCV jumped from $38.0bn at end-2025 to $105.8bn, including a $45bn Anthropic deal for the Monarch campus in West Virginia.
  • H1 2026 losses reached $1.02bn on $140.6m revenue; full-year 2025 revenue was $33m.
  • Anthropic exercised rights over Building 2 on September 29, 2026; Nscale has no financing agreements yet and targets a $30bn IPO valuation.

The story

Nscale has doubled its active GPU fleet to 50,000 machines since late August, according to an updated IPO prospectus that shows the neocloud adding two data centers and 25,000 GPUs in roughly two and a half months. That's still barely 11 percent of the 461,000 GPUs the company has told investors it will deploy.

The September prospectus, dated August 31, 2026, listed just 25,000 active GPUs — around five percent of the goal. The pace has quickened. Whether it quickens enough is the question the IPO will answer.

What do the new numbers show?

Nscale now runs seven active data center sites, up from five with 55MW, and has ten more in the pipeline. The company did not disclose total capacity across the seven live sites.

The power ledger is more forthcoming. Nscale claims 1.37GW of active and contracted capacity: 1GW at owned sites, 200MW at leased sites, and 165MW at colocation facilities. It also claims "line of sight" to 10GW of potential power capacity across its footprint. Line of sight, one notes, is not a contract.

How are the finances reported?

The company has quietly changed its reporting period. The previous prospectus flagged revenue of $140.6 million for the six months to June 30, 2026 — a claimed 1,252 percent jump year-on-year — alongside losses that ballooned to $1.02 billion, up from $368.9 million in the same stretch of 2025.

The new filing instead emphasizes full-year 2025: revenue of $33 million, up 73 percent from $19.1 million in 2024. A 73 percent growth story reads more gently than a $1 billion loss. Investors will do the arithmetic themselves.

The contract book is where the money supposedly lives. "As of the date of this prospectus, we had approximately $6.4 billion of active and $105.8 billion of active and contracted TCV (total contract value) under long-term take-or-pay contracts with customers, compared to $0.5 billion of active and $38.0 billion of active and contracted TCV as of December 31, 2025," the filing states. Those contracts underpin the roughly 461,000 GPUs active or contracted to date.

What is happening with Anthropic?

The filing adds detail on the $45 billion compute agreement Nscale and Anthropic signed in August for the Monarch Compute Campus in West Virginia. It confirms a second building is now in play.

"On September 29, 2026, Anthropic exercised their right to contract for additional compute at Building 2 on our Monarch campus. We and Anthropic have 60 days (subject to mutual extension) to negotiate an agreement in good faith," the prospectus says. Anthropic may also trigger rights over Building 3 within 15 business days after the Building 2 agreement is signed, with a further 60 days to finalize terms.

The money for all this does not yet exist. Nscale says it expects to fund the Anthropic deployments through "external financing and cash flow from operations." It has tested market depth and cites a track record of data center and GPU financings — but concedes it has no financing agreements in hand.

"Based on these efforts and our track record, we believe we will be able to obtain the qualifying financing within the required period," the company said. Belief is doing heavy lifting in that sentence.

There is a penalty clause worth watching. If Nscale fails to deliver GPU infrastructure to Anthropic on schedule, including through supply chain delays, "Anthropic may be entitled to terminate that tranche without liability."

When does the IPO land?

Nscale reportedly aims to raise billions to fund its AI data center build-out and is targeting a valuation of around $30 billion. No official date for the offering has been set. Until it prices, the market gets to judge a company with 50,000 live GPUs, $33 million of 2025 revenue and a $105.8 billion contract book it must now build, power and finance on time.

Also reported

Share this article:

« PreviousNext »

More from Amara Osei

Amara Osei

Show full bio

News editor covering technology and product news in Carrier business, 5G and 6G, fiber and broadband at Telecom Gazette.

527 articles