Integra Files for $8 Billion, 756MW Data Center Campus in Quanah, Texas
19000-200 Holdings, linked to Integra, has filed for an $8 billion, 756MW data center campus in Quanah, Texas, with construction set for November 2026 through December 2028.
Networks & InfrastructureWhy it matters
- 19000-200 Holdings, LLC filed for a $8 billion data center in Quanah, Hardeman County, Texas.
- The single-story facility would cover 288,355 sq ft (26,790 sqm) at 4628 Four Corners Road.
- Construction is slated to run from November 2026 to the end of December 2028.
- The campus could total 756MW according to project documentation linked to Integra.
- Quanah is less than 30 miles from Childress, where Iren and Crusoe are building data centers.
The story
An $8 billion data center campus of up to 756MW has been filed for regulatory approval in Quanah, Hardeman County, Texas, according to an application lodged with the Texas Department of Licensing and Regulation by 19000-200 Holdings, LLC.
The application, first reported by DatacenterDynamics, describes a single-story facility of 288,355 sq ft (26,790 sqm) at 4628 Four Corners Road on the outskirts of Quanah, a city of roughly 2,300 residents that serves as the seat of Hardeman County near the Oklahoma state line. Construction would begin in November 2026 and finish by the end of December 2028. That is a 26-month build schedule for a campus whose total investment the filings put at $8 billion.
Who is behind the project?
The listed address of 19000-200 Holdings, LLC matches that of Integra, a data center solutions provider specializing in turnkey construction and infrastructure services. A dedicated project website maintained by Integra, which refers to the development internally as the 'clocktower' project, indicates the full campus could reach 756MW of capacity.
Integra has not disclosed which end user or users the facility would serve. That absence of a named tenant is common in hyperscale development, where cloud and AI operators typically contract capacity through intermediaries before public identification. The scale of the investment, however, places the project firmly in the tier of campuses built for a single anchor tenant rather than for colocation resale.
The design specifies closed-loop cooling systems intended to reduce water consumption. Water use has become a flashpoint in data center permitting across Texas and the arid Southwest, where local authorities have pushed back against high-demand facilities. A closed-loop architecture recirculates coolant rather than drawing continuously on municipal supply, a choice that can ease approval in small municipalities with limited water infrastructure.
What does this change for the region?
Quanah sits less than 30 miles from Childress, where Iren and Crusoe are already developing data center campuses of their own. The Integra filing effectively establishes a second North Texas cluster node along the US-287 corridor, bringing hyperscale-scale power demand to a county with no prior history of such facilities.
For local officials, the arithmetic is straightforward. An $8 billion capital project in Hardeman County, whose entire population is under 4,000, would represent investment on a scale the regional economy has never absorbed. Tax base, construction employment and long-term operations staffing all follow from the build, though the filing itself does not specify headcount.
The city takes its name from Quanah Parker, the last chief of the Comanche, a historical note that now attaches to one of the larger single-campus data center proposals in the state.
What happens next?
The application now sits with the Texas Department of Licensing and Regulation, which reviews building plans against state code. If the timetable in the filing holds, site work would begin in November 2026, with the first phase targeted for completion by December 2028. Confirmation of an anchor tenant, the identity of the power provider and the phasing of the 756MW build-out remain the open questions that will determine whether the schedule survives contact with utility interconnection timelines.