DC Blox seeks approval for 500,000 sq ft third Atlanta West hall

DC Blox has filed with Georgia regulators for a 500,000 sq ft, 80MW third building at its Atlanta West campus, raising the Douglas County site to 200MW by December 2029.

3 min read

DC Blox files for third building at Atlanta West data center campusNetworks & Infrastructure
DC Blox files for third building at Atlanta West data center campusPexels / pixabay

Why it matters

  • DC Blox filed for a 500,000 sq ft (46,450 sqm) third building, ATL1-C, at its Atlanta West campus in Douglasville, Georgia.
  • Full build-out of the 100-acre campus is set at 200MW across three buildings and 1.37 million sq ft, with completion targeted for December 2029.
  • The first two buildings, 80MW Building A and 40MW Building B announced in November 2023, are leased; the final 80MW hall is available.
  • DC Blox broke ground on its 216MW Atlanta East campus in Conyers in October 2024.
  • The company is backed by Bain Capital Credit and Post Road Group.

The story

DC Blox has filed for a third data center building of 500,000 sq ft (46,450 sqm) at its Atlanta West campus, lifting the Douglas County, Georgia site to a planned 200MW at full build-out.

The US operator submitted a development of regional impact notice this week with the Georgia Department of Community Affairs for the project, designated ATL1-C. The building would sit at 1800 N River Road in Douglasville. The filing names December 2029 as the completion date.

For operators and colocation buyers, the numbers matter more than the filing itself. The third hall takes the campus from a previously planned 180MW to 200MW, and from 760,000 sq ft (70,605 sqm) to 1.37 million sq ft (127,277 sqm) across three buildings on a site that has grown from 55 acres to 100 acres.

What has changed since 2023?

DC Blox first announced the Atlanta West campus in November 2023. The original plan covered two buildings on the ATL1 West site: an 80MW Building A and a 40MW Building B, plus a substation. That configuration promised 180MW across 760,000 sq ft on 55 acres.

Reports that a third building was under consideration surfaced in 2024. This week's filing confirms the expansion and attaches concrete parameters to it: 500,000 sq ft, 80MW, and a December 2029 completion target.

The company's website states that the first two buildings on the site are fully leased, while the final 80MW building remains available. That leasing position suggests the expansion reflects demand already absorbed on the campus rather than speculative capacity alone — though the company has not disclosed tenants or contract terms.

Where does this fit in DC Blox's footprint?

DC Blox is backed by Bain Capital Credit and Post Road Group. The company operates facilities in operation and development across Alabama, Georgia, South Carolina, North Carolina, Indiana, and Tennessee, along with cable landing stations in South Carolina and Florida.

In the Atlanta metro area, the company runs one existing facility in the Brookhaven area at 6 West Druid Hills Drive. That site spans 3,350 sq ft (311 sqm), runs on two 1MW generators, and carries 6,470 sq ft (600 sqm) of expansion potential — a fraction of the scale now planned in Douglas County.

The operator is also building elsewhere in the region. It broke ground on its Atlanta East campus in Conyers, Rockdale County, in October 2024. That site will offer 216MW of capacity, making it larger than Atlanta West even after the third building.

What does the timeline look like?

The filing sets a December 2029 completion for ATL1-C, giving the project a roughly five-year runway from the current notice. No construction start date appears in the filing summary.

Key parameters of the expanded campus:

  • Total capacity: 200MW across three buildings at full build-out
  • Total space: 1.37 million sq ft (127,277 sqm)
  • Site size: 100 acres in the Douglasville/Lithia Springs area
  • New building: ATL1-C at 500,000 sq ft (46,450 sqm), 80MW
  • Completion target: December 2029
  • Leasing status: Buildings A and B leased; ATL1-C available

Between Atlanta West at 200MW and Atlanta East at 216MW, DC Blox is positioning more than 400MW of capacity across the Georgia metro market, with the Douglasville third hall now moving through the state regulatory process toward a 2029 delivery.

Also reported

Share this article:

« PreviousNext »

More from Daniel Okafor

Daniel Okafor

Show full bio

Senior reporter covering regulation, policy and their impact on Carrier business, 5G and 6G, fiber and broadband at Telecom Gazette.

582 articles