Loudoun County votes 7-1 for 12-month data center moratorium
Loudoun County, Virginia, paused new data center and substation applications for up to 12 months, with 33 active cases and $1.3 billion in projected 2027 budget revenue.
Networks & InfrastructureWhy it matters
- Loudoun County paused new data center and substation applications for up to 12 months, backdated from September 15, 2026.
- The moratorium vote passed 7-1 with one abstention and will expire in September 2027.
- Loudoun lists 245 operating or developing data centers and 33 active legislative applications.
- Data centers are projected to generate $1.3 billion, or 40% of the county’s 2027 budget.
- A proposed Virginia statewide moratorium would run for three years from July 1, 2027.
The story
At this week’s meeting, the Loudoun County Board of Supervisors voted 7-1, with one abstention, to halt consideration of new data center and substation applications for no more than 12 months.
Backdated from September 15, 2026, the pause will run until September 2027.
County staff recommended approval of the measure.
The resolution gives the county up to 12 months to finish updating its data center policies.
The pause affects a global center of data center development in Northern Virginia, where Loudoun counts 245 data centers in operation or under development and 33 active applications.
The county’s 2027 budget projects $1.3 billion in data center revenue, or 40 percent of the total budget.
Why did the county choose a pause?
County officials first moved in July to explore the legality of a data center moratorium.
In September, the board directed staff to prepare the resolution wording.
County staff deemed a permanent ban unworkable under Virginia law, leading the board to adopt a temporary pause instead.
That legal constraint matters because the resolution caps consideration at no more than 12 months rather than removing development rights indefinitely.
Supervisor Juli Briskman, who led the proposal, said:
“This is a major step forward for our residents and communities who have been increasingly vocal about the impacts of data centers.”
Briskman gave a second reason for bringing the proposal forward:
“I first brought this proposal forward in July because I believe the board should not continue to approve data centers and substations while we are actively working to strengthen the regulations that govern their development.”
What does the moratorium change?
The resolution pauses county consideration of new applications, without announcing the closure of operating data center facilities.
Parcels already grandfathered keep their by-right status, although county officials could remove that protection later.
The 33 active legislative applications will remain in a backlog after the pause, rather than receiving a decision before then.
The measure changes the approval timetable rather than the operating status of existing facilities.
That $1.3 billion projection gives the delay immediate fiscal context: data centers account for 40 cents of every projected budget dollar in 2027.
How large is the application backlog?
A county information fact sheet counts 245 data centers in operation and under development across Loudoun County.
Meeting documents indicate 33 active legislative applications:
- 10 data center applications.
- 12 applications for non-reliability or combined substations.
- 1 application for a grid-reliability substation.
- 10 applications for combined data centers and substations.
Staff expect a large backlog by September 2027 and plan to limit applications at each board meeting so public hearings remain manageable.
Staff also say clearing the backlog after the moratorium could take months, extending uncertainty beyond the nominal 12-month pause.
The pipeline includes both computing projects and the substations needed to serve them, so power infrastructure remains tied to the same approval timetable.
What legal and investment risks follow?
A speaker representing the Data Center Coalition urged the board not to change course abruptly, warning that the pause creates uncertainty, invites legal challenges and disrupts investments.
County staff said the adopted measure could lead to lawsuits from developers.
For developers, the practical effect is delay before review and possible additional delay through litigation.
Those risks sit beside 245 operating or planned facilities and 33 active legislative cases, so the commercial stakes extend beyond new entrants.
How did Loudoun reach this point?
For 25 years, Loudoun County classified data centers as similar to offices, granting by-right zoning wherever office buildings were allowed under county rules.
The combination of permissive zoning and economic and tax incentives supported continued data center growth.
By 2016, Loudoun had become home to the world’s largest concentration of data centers.
In 2025, however, the county ended by-right development for most data centers, requiring new projects to undergo full review and public scrutiny.
Land parcels with existing applications and zoning were grandfathered in to keep their by-right status, although the county could remove that protection later.
The new moratorium extends that regulatory shift from project-by-project scrutiny to a temporary halt in consideration.
Could the block widen across Virginia?
Virginia state Sen. Russet Perry, a Democrat representing Loudoun County, recently proposed a statewide moratorium lasting three years from July 1, 2027.
If enacted, her proposal would stop state agencies from approving data center planning applications across Virginia.
It remains separate from Loudoun’s resolution, but the two measures would constrain approvals on different schedules.
Across the United States, cities, counties and townships introduced or enacted hundreds of data center moratoriums over the previous two years.
Data centers became a major issue in the November 2026 U.S. midterms, with many voters rejecting the industry at the ballot.
Virginia’s policy picture is not uniform.
Spotsylvania County voted this week to advance a special use permit for the 550-acre Crossroads Technology Campus in the Lee Hill area.
Amazon is reportedly the campus’s end user.
That approval path continues while Loudoun freezes consideration, creating two separate development tracks within the same state.
For Loudoun developers and investors, the next fixed date is September 2027, when the moratorium expires and staff expect to resume a backlog that could take months to clear.
Perry’s proposed statewide stop would begin on July 1, 2027, while developer litigation could extend the local delay.
Policy revisions, lawsuits and permit reviews will determine whether the pause redirects investment or merely postpones it.