Data Centers Still Chasing Megawatts as Voters Turn Cold

DCD Connect Virginia heard that power delays, not politics, remain the industry's core problem, after midterm voters rejected most local data center measures.

3 min read

DCD Connect Virginia 2026: It’s all about the power (and public perception)Networks & Infrastructure
DCD Connect Virginia 2026: It’s all about the power (and public perception)blickpixel / pixabay

Why it matters

  • This month's US midterms saw voters reject most local data center measures; more than half of polled voters cited data centers as a voting factor.
  • Hyperscalers are reportedly walking away from leases where project timelines slip too far.
  • OpenAI and Anthropic are reportedly seeking 20-30MW deployments for inference workloads.
  • Some AI and neocloud customers request networking rooms of up to 400 racks.
  • 800VDC power is the next technology shift under discussion, with 1MW racks a future prospect.

The story

By Amara Osei

Voters rejected most local data center measures in this month's US midterms, and more than half of polled voters said data centers shaped how they cast their ballot. Industry executives got that news on the morning of day two at DCD Connect Virginia, the fifth edition of the conference, held in the heart of the world's largest data center market. It was the biggest iteration yet. The timing could have been kinder.

The event drew more mainstream coverage than any niche infrastructure conference could reasonably expect, some of it framing the industry as "crashing out" — and accusing executives of playing pickleball during an election week that went badly for them. Politics surfaced in almost every panel. Yet for most attendees, the real fight remained speed-to-power.

Why is power still the bottleneck?

Grid connection delays and the time to bring IT capacity online topped the worry list, ahead of moratoriums and public sentiment. Hyperscalers are reportedly walking away from lease agreements where project timelines have slipped too far.

Natural gas remains the short-term "bridge" solution, as it has for the past two years, with modular construction speeding up build times. Speakers acknowledged the current pace makes sustainability "more difficult, but not less important."

One message rang clearest: data centers need to be a grid resource, not a hindrance. Operators were urged to work with utilities to smooth demand and avoid disturbances like the one narrowly avoided in Virginia last year. One hyperscaler proposed a collegiate approach — operators pooling capacity planning with grid providers rather than each requesting individual upgrades.

What does the mid-sized market offer?

Reports that OpenAI and Anthropic are seeking deployments in the 20-30MW range for inference workloads have buoyed some operators. That sub-50MW segment — hyperscale by pre-LLM standards — now reads as an easier sell to locals and a lighter lift on grid capacity.

The election damage was undeniable. Anti-data center senators, representatives and governors won their races. But the conference vibe was less lament, more logistics: how to move projects forward smarter.

Can the industry rebuild trust?

There was a collective admission that the industry hasn't done enough to earn public trust and is now paying for it. Misinformation came up repeatedly. Some argued residents soften their opposition when given accurate information on water use, energy bills and ratepaying. Others countered that debunking doesn't matter if nobody believes you in the first place.

Transparency helps, speakers said, but choice matters more. Developers too often arrive with facts and a checkbook, telling residents what a project will be rather than offering feedback that meaningfully changes it. Threatening to take projects elsewhere rarely lands well, even when a community might later miss the tax dollars.

Ratepayer pledges and dropping non-disclosure agreements are a start — and only a start. "You can have a community that works with you, or fights you at every step of the way," one panelist said.

One operator prescribed regular community meetings, warning that early attendees will be angry and uninterested in learning. Operators simply have to "take the punches." Show up enough, the theory goes, and anger subsides into curiosity. "Let them hate data centers as an industry," another panelist said, "as long as they love us as local partners."

What's next on the technology roadmap?

Fiber demand from AI and neocloud customers could become astronomical, the audience heard. Real demand for low-latency inferencing may drive new local fiber, carrier hotels and exchange points in areas traditionally routed to distant hubs. Some AI and neocloud customers are already asking for networking rooms of up to 400 racks, before counting the compute.

Liquid cooling, a hot topic in prior years, has settled into routine — the industry now deploys direct-to-chip and hybrid air/liquid setups comfortably, at least in new builds. The next shift on the horizon is 800VDC power. It's too early for definitive answers, but if Nvidia's promised rack density increases materialize, 1MW racks loom as a potentially scary proposition. We're not there yet. Nobody left Virginia pretending otherwise.

Also reported

Share this article:

« PreviousNext »

More from Amara Osei

Amara Osei

Show full bio

News editor covering technology and product news in Carrier business, 5G and 6G, fiber and broadband at Telecom Gazette.

527 articles