Ottawa, Kansas Voters Impose 10-Year Ban on Large Data Centers

Voters in Ottawa, Kansas backed a 10-year ban on data centers over 25MW with 71.85% support, capping a campaign sparked by a scrapped 450MW project at Proximity Park.

2 min read

10-year data center moratorium approved in Ottawa, KansasTelecom Business
10-year data center moratorium approved in Ottawa, KansasAurusdorus / pixabay

Why it matters

  • 71.85% of Ottawa, Kansas voters backed a 10-year moratorium on data centers larger than 25MW in the 2026 midterms.
  • The campaign followed a proposed 450MW data center and gas power plant at the 300-acre Proximity Park site.
  • Ottawa City Commission terminated the land sale to Lightfield Energy LLC in September after 18+ months of talks failed.
  • Emporia and El Dorado, Kansas also approved data center moratoriums; over 40 similar measures passed nationwide.
  • Campaign group Ottawa United united Republicans, Democrats and unaffiliated voters behind the ban.

The story

Voters in Ottawa, Kansas, have approved a 10-year moratorium on large-scale data centers, with 71.85 percent backing the ban in a ballot held alongside the 2026 US midterm elections last week. The ordinance blocks any data center with a capacity of more than 25MW in the city, located in Franklin County, Kansas.

The result marks a clear win for Ottawa United, a residents' campaign group that formed to oppose data center development after a 450MW facility was proposed for Proximity Park, a 300-acre site in Ottawa. The group built an unusually broad coalition for a local single-issue campaign.

Jessica Christopher of Ottawa United told KMBC News the effort drew support from across party lines. "It was a mix between Republicans and Democrats and a bunch of unaffiliated voters," she said. "And we all just came together for a common good, which is why we named it Ottawa United."

Why did residents mobilize?

The campaign reflects the wider grassroots opposition to data center construction that has spread across the United States in recent months, driven by concerns over power consumption, land use and the industrial footprint of hyperscale facilities. A 450MW campus ranks among the larger projects of its kind, comparable in scale to the power demand of a small city rather than a neighborhood substation.

In Ottawa's case, the fight had a twist. The project that triggered the backlash was already dead by the time voters went to the polls. The Ottawa City Commission had agreed to sell the Proximity Park land to developer Lightfield Energy LLC, which planned to build both a data center and a natural gas power plant on the site.

After more than 18 months of negotiations, the parties failed to reach a development agreement, and councilors terminated the sale at a meeting in September. The moratorium vote therefore closes the door on any future revival of the scheme, and on any comparable project for the next decade.

Is Ottawa part of a wider trend?

Yes. Two other Kansas communities, Emporia and El Dorado, approved data center moratoriums in the same elections last week. Across the United States, more than 40 similar pieces of legislation were backed by voters at the midterms.

For operators and developers, the pattern signals a hardening political environment for site selection. Ballot-box bans in mid-sized markets like Ottawa — communities often courted for cheap land and available power — add a new layer of local risk to expansion plans that previously faced mainly zoning and utility constraints.

The 25MW threshold in Ottawa's ordinance is strict enough to rule out even modest hyperscale builds while leaving small enterprise facilities, well under that capacity, theoretically unaffected. With the ban set to run for 10 years, any developer eyeing Franklin County will now need to look elsewhere or wait until the mid-2030s for the ordinance to lapse or be revisited.

Also reported

Share this article:

« PreviousNext »

More from Elena Vasquez

Elena Vasquez

Show full bio

Market editor covering companies, deals and strategy in Carrier business, 5G and 6G, fiber and broadband at Telecom Gazette.

513 articles