Macquarie Files Plans for AU$2bn, 200MW Sydney Data Centre Campus

Macquarie Data Centres has filed SEARS plans for a 200MW, AU$2bn campus at Macquarie Park, Sydney — more than tripling its current 65MW footprint, though no timeline was disclosed.

3 min read

Macquarie Data Centres eyes 200MW campus in Sydney, AustraliaNetworks & Infrastructure
Macquarie Data Centres eyes 200MW campus in Sydney, Australiaengrahmad2653 / pixabay

Why it matters

  • Macquarie Data Centres filed a SEARS application for a 200MW, 42,015 sqm campus at 2 Alma Road, Macquarie Park, Sydney.
  • The project carries an estimated investment of AU$2 billion (US$1.35 billion); no development timeline was disclosed.
  • The new campus would more than triple Macquarie's existing 65MW across 30,000 sqm in the Macquarie Park corridor.
  • The 47MW IC3 Super West facility was topped out in December 2025.
  • The 3.4-hectare site was subdivided from 66 Talavera Road, home to a 2015 office building occupied by AstraZeneca.

The story

Macquarie Data Centres has filed to build a 200MW data centre campus in Sydney at a projected cost of AU$2 billion (US$1.35 billion), roughly triple the capacity it currently operates across its entire Macquarie Park portfolio.

The application, lodged with the New South Wales Government under the SEARS process, covers the proposed Macquarie Engineering and Technology Campus at 2 Alma Road in the Macquarie Park area of the city of Ryde. Plans call for a 42,015 sqm (452,245 sq ft) facility of up to six stories, with existing office buildings on the site to be demolished.

What the filing does not include is a timeline. No construction start date, staged delivery schedule or target energisation year appears in the application, which means the 200MW figure remains an ambition tied to planning approval rather than a committed build.

How big is 200MW in context?

The campus would sit on approximately 3.4 hectares — land recently subdivided from the neighbouring plot at 66 Talavera Road, which holds a 2015-vintage office building occupied by pharmaceutical company AstraZeneca.

For scale: Macquarie Technology Group, founded in 1992, currently runs two buildings in the Macquarie Park corridor, IC2 and IC3 East, and has a third, IC3 Super West, in development. Together they total 65MW across 30,000 sqm (322,915 sq ft). The new campus would deliver more than three times that capacity on a single site, at more than four times the floor area.

The company topped out the 47MW IC3 Super West facility in December 2025, giving it a concrete near-term capacity addition already in motion. It also operates IC1 in Sydney's central business district and two bunker data centres in Canberra.

A quietly expanding land strategy

The Alma Road filing follows a pattern. In July 2025, Macquarie said it would buy additional Sydney land for a new data centre but disclosed little beyond a target of 150MW of new capacity. The SEARS application now puts a name, a site and a larger number — 200MW against the earlier 150MW signal — on that intention.

The investment figure, AU$2 billion, works out to roughly AU$10 million per megawatt of planned capacity, a frame investors can use to benchmark the project against other hyperscale-adjacent builds in the Australian market. As always with early-stage filings, the headline number covers a full build-out; the application does not break down phasing or how much capital is committed before approval.

What happens next

The proposal now rests with the New South Wales planning system. SEARS — the Secretary's Environmental Assessment Requirements — obliges the developer to prepare a full environmental impact statement before major state-significant projects proceed, a process that typically shapes power procurement, noise and traffic conditions for facilities of this size.

With IC3 Super West topped out and the Alma Road application lodged, Macquarie has positioned itself to add capacity in stages through the second half of the decade, contingent on approval and on the timelines the company has so far declined to share.

Also reported