Milan to Pass Dublin as Europe's Fifth-Largest Data Center Market by 2028
CBRE forecasts 255MW of new hyperscaler capacity will lift Milan past Dublin by 2028, as European colocation take-up exceeds new supply for the first time.
Networks & InfrastructureWhy it matters
- Milan to add 255MW of hyperscaler capacity by 2028 and overtake Dublin as Europe's fifth-largest data center market
- Italy's data center market has grown sixfold since 2020
- European colocation take-up hit 1.34GW against 1.26GW of new supply — a first for Europe
- European vacancy expected to fall to 10.3% by year-end from 12.3%
- Milan and Dublin are separated by 100MW of operational capacity
The story
Milan will add 255MW of data center capacity by 2028 and overtake Dublin as Europe's fifth-largest market, according to CBRE's Q3 2026 European Data Centers report. Every megawatt of that pipeline is earmarked for hyperscalers building out announced cloud regions, with most of it landing in west Milan.
The Italian market has grown sixfold since 2020, CBRE says. Milan also posted the highest take-up among the ten secondary markets the firm tracks, a list that includes Berlin, Brussels, Madrid, Munich, Oslo, Stockholm, Warsaw, Vienna and Zurich. That demand, the report notes, reflects a wider shift toward non-core markets where power is available and cheaper.
"Milan's accelerated development trajectory highlights the city's transition from a secondary market into a top European data centre hub," said Andrew Jay, head of Data Centre Solutions, Europe, at CBRE. "This evolution reflects a broader geographic diversification of data centre activity, with Southern Europe growing in relevance when compared to traditional data centre clusters, namely Frankfurt, London, Amsterdam, Paris, and Dublin (FLAPD)."
How close is the race?
Not very, at the moment. Milan and Dublin sit just 100MW apart in operational capacity, so 255MW of hyperscaler construction does the arithmetic on its own. Dublin's problem isn't demand — it's the grid.
Ireland effectively banned new data center grid connections in Dublin until late last year, when it replaced that regime with new rules. Operators seeking a connection must now install on-site generation and battery systems covering the facility's full electricity demand, and feed excess power back to the grid when needed. Several environmental groups are challenging those rules in Ireland's High Court, so the legal ground is not entirely settled.
Dublin still showed some fight in Q3. Its take-up beat every other core market, driven by a single hyperscaler moving into vacant space on one campus. CBRE calls that "unusual," given how cautious operators remain about the market. One tenant does not a recovery make.
What happened to European supply overall?
Vacancy is tightening. CBRE expects European vacancy to fall to 10.3 percent by year-end, down from 12.3 percent a year earlier.
Colocation demand is now outrunning construction. Europe delivered 1.26GW of new supply, against 1.34GW of take-up — the first time on record that take-up has exceeded colocation supply delivered in Europe. CBRE attributes the gap to AI infrastructure demand from neoclouds and hyperscalers.
Geography shifted within the quarter, too. London, Paris and Dublin accounted for more than half of Q3 take-up, reversing the previous quarter, when continental European markets carried the majority.
The pattern is straightforward. Power constraints and planning friction are pushing hyperscalers toward Southern Europe, and Milan has the land, the grid headroom and the cloud-region commitments to absorb them. Whether Dublin's new connection rules survive the High Court will decide whether the 100MW gap widens or holds.
— Amara Osei