Carriers & OperatorsVirtual Power PlantsEnergy StorageGrid FlexibilityRevenue Diversification
Telcos Turn Backup Batteries Into Grid Revenue: VPP Market Headed to $30B
Elisa earns €800 per site from VPP battery dispatch as Frost & Sullivan projects a near-$30B market by 2035; wear modelling and uneven EU rules remain the catch.
Carriers & OperatorsWhy it matters
- Frost & Sullivan values the VPP market at $5.5–5.7 billion, reaching ~$29–30 billion by 2035 (20–22% CAGR)
- Elisa in Finland earns ~€800 additional revenue per site; Central European operators report €300–€1,000 per site
- Zhejiang Mobile built a 250 MWh / 22 MW system across 5,000 sites, saving CNY 28.3 million over two years
- Huawei's NetEco platform pools up to 10,000 sites; ~200 sites equal one megawatt of capacity
- VPP deployments now span more than 14 countries; Asia Pacific expected to exceed 30% CAGR
The story
By Rebecca Stone
Finland's Elisa is generating roughly €800 in additional revenue per site by feeding its backup batteries into virtual power plant schemes — one of the more concrete numbers in a telecom energy market that Frost & Sullivan expects to grow from $5.5–5.7 billion today to nearly $29–30 billion by 2035.
That forecast, a compound annual growth rate of 20–22%, comes from Gautham Gnanajothi, Global Senior Vice President of Research at Frost & Sullivan, who joined Li Shaolong, President of Site Power Facility Domain at Huawei, and Adele Nardo, Business Development Manager at aggregator Hive Power, for a roundtable on telecom VPPs. Their central claim: the batteries operators already own at thousands of sites are dormant assets that can be dispatched for grid flexibility without compromising backup power.
The claim deserves scrutiny, but the early results are not trivial.
Why now?
Gnanajothi frames three pressures on operators. Data traffic keeps rising, and infrastructure and power requirements rise with it — but revenue does not match pace. Energy price volatility is now a daily phenomenon, as Nardo notes: morning prices differ from afternoon prices. And in Europe, 30.8% of electricity production comes from wind and solar, which introduces grid volatility that flexibility services can monetise.
Infrastructure constraints help the case. A grid upgrade for new assets can take 4–10 years in Europe, Nardo said, while VPP schemes exploit installations that already exist and are already secured.
Li adds the industry shift: "Three years ago, almost no telecom operators were participating in the VPP business." Operators bought batteries purely to power main equipment during outages. At the ICT summit in Bordeaux, France, three years ago, he met operators who did not know what VPP could deliver. Now, he says, knowledge has spread beyond Europe.
How does Huawei's solution work?
The technical problem is that VPP-dispatchable batteries need significantly higher quality than backup batteries, and operators — running 2G through 5G networks with 6G on the horizon — prioritise resilience. Huawei's answer is one battery supporting backup, solar and VPP scenarios, plus one IoT module and one platform.
The capacity split is specific. A 100Ah battery can reserve 60Ah for backup and offer 40Ah to the VPP, with Huawei's software calculating the optimal dispatchable capacity. The company's NetEco platform can manage up to 10,000 sites; around 200 sites aggregate to one megawatt, and at 2,000 sites the portfolio is large enough to provide grid services.
Nardo, whose company aggregates assets for market participation, confirms the single-interface pre-aggregation helps, but flags what the vendor pitch leaves out. Tracking battery wear against market profit is a barrier; Hive Power applies degradation models to ensure "trading doesn't outlast battery lifetime." Telemetry and metering requirements also differ by country — and even between distribution system operators within one country, forcing phased rollouts.
Revenue uncertainty is the operators' main worry. Nardo lists the mitigations: pure merchant exposure, structural floor agreements with fixed revenue, or tolling agreements, backed by forecasting models.
What are the measured results?
Beyond Elisa's €800 per site in Finland, deployments now span more than 14 countries. In Japan, NTT DoCoMo and Hokkaido Electric Power use base station batteries for demand response. In China, Zhejiang Mobile built a 250 MWh / 22 MW storage system across 5,000 sites and assembled a 30 MW communications network VPP that saved close to CNY 28.3 million in electricity costs over two years.
In Central Europe, Nardo reports per-site revenue between €300 and €1,000. Operators investing in fully bidirectional batteries for trading can reach around €200,000 per megawatt per year when assets are aggregated. The caveat: those figures depend on market access, and the next step — dynamic value stacking across local flexibility programmes and balancing services — only works where markets admit aggregated resources.
Regulatory context matters here. Since 2019, the EU's electricity market directive has pushed distributed energy resources into standard energy markets. Huawei, first to publish a VPP solutions white paper at MWC Barcelona 2024, contributes to VPP standards within ITU-T Study Group 5 and has worked with the GSMA and telcos since 2023. It won a Frost & Sullivan 2025 award for Global Technology Leadership Innovation in VPP solutions — an award whose evaluation criteria included commercial tangibility, though it is worth noting Frost & Sullivan both granted the award and supplied the market forecast in this discussion.
What still blocks scale?
All three participants converge on the same gap: harmonisation. Balancing markets — aFRR, mFRR, even FCR — remain unevenly open to distributed resources across European countries, with extreme zonal differences. Gnanajothi argues no single player can push adoption alone and that "if regulations become a little more lenient, that would push adoption further." Asia Pacific, where he expects more than 30% CAGR over the next five to eight years, may move faster than a fragmented Europe.
The economics still hinge on conservative, price-sensitive operators being convinced that ring-fenced backup capacity is genuinely safe. Huawei's pitch is minimal investment and maximum revenue; Hive Power's is commercial models that shield operators from market volatility. Both promise more than the €1,000-per-site ceiling over time — but only if regulators keep opening the markets that make the revenue real.