Networks & InfrastructureReliance JioLeo SatellitesSatellite BroadbandSatellite Manufacturing
Reliance's 1,600-Satellite LEO Plan Slips to 2035
Reliance is courting Indian and US manufacturers for a 1,600-satellite LEO broadband network backing Jio, with completion now slated for 2035 after a five-year slip.
Networks & InfrastructureWhy it matters
- Reliance plans a 1,600-satellite LEO broadband constellation, with completion pushed to 2035 from 2030.
- India builds fewer than 15 satellites a year; the constellation needs around 200 annually.
- At least 400 satellites would be imported from the US; China is excluded as a supplier.
- A test mission is slated for September 2027, wider deployment from early 2028.
- Musk accused 'certain oligarchs' of delaying Starlink's India entry; Reliance denied it.
The story
Reliance wants 1,600 satellites in low-Earth orbit, and it wants most of them built somewhere other than China. According to Bloomberg, the Indian conglomerate is negotiating manufacturing partnerships with domestic satellite makers, technology startups and industrial groups, offering to fund the infrastructure needed to scale production. Talks are also under way with two US firms, with European suppliers being weighed as well. China, the sources said, is off the table.
The arithmetic explains the urgency. India currently produces fewer than 15 satellites a year. The proposed constellation needs output of roughly 200 annually. Reliance's answer is a hybrid approach: build at home where it can, and import the rest — at least 400 satellites from the US — to work around the domestic capacity gap.
What would the network actually do?
The LEO constellation would back the expansion of Jio Platforms, the newly listed telecoms unit that owns mobile operator Reliance Jio. Its primary job is extending connectivity across India, with remote areas the obvious target. Strategic communications is a secondary use the sources didn't rule out. Think of it as Jio's coverage map getting a ceiling: the same customers, reached from 500-odd kilometres up rather than from a tower that isn't there.
The timeline, however, has stretched. A test mission is slated for September 2027, wider deployment from early 2028, and completion by 2035. That final date sits five years beyond the previous 2030 target, a slip Bloomberg attributes to manufacturing and launch constraints. In satellite terms, a half-decade delay is less an admission than an estimate finally matching reality.
Where does Starlink fit in?
The project is unmistakably a domestic counterweight to Elon Musk's Starlink, which is still waiting on regulatory clearances for its own India launch. The two billionaires have not been quiet about it. Last month, Musk accused "certain oligarchs" of delaying Starlink's entry to protect incumbent operators. Reliance rejected the charge and pointed out its own satellite service is also stuck awaiting approvals. Both sides, in other words, claim to be the one standing in line.
That regulatory standoff matters for the commercial picture. Whoever clears India's approvals first gets a head start on the enterprise and government connectivity market, and Reliance's manufacturing negotiations suggest it intends to be a contender rather than a bystander. A constellation you build yourself is harder to block than one you import wholesale — though, with 400 US-built satellites in the plan, not entirely self-built either.
The commercial reality, meanwhile, sits some distance from the ambition. No contracts have been signed with manufacturers, no satellites have launched, and the production ramp — from 15 units a year to 200 — does not yet exist anywhere in India. Reliance is offering to fund the infrastructure to change that, which tells you the money is ready even if the factories aren't.
For Jio Platforms, the constellation would extend a franchise that already leads India's mobile market into territory terrestrial networks reach poorly or not at all. The newly listed unit gives the group a market currency to finance the effort; the satellites give it a story that goes beyond price-war margins.
Whether 2035 holds this time depends on things a balance sheet can't fix: launch slots, supply chains and a satellite industry India hasn't yet built. The test mission in September 2027 will be the first hard checkpoint.
Also reported