QTS evacuates Georgia construction areas after shooting threat letter

Police evacuated parts of QTS's planned 250MW Fayetteville data center campus after a shooting threat; QTS said no customers were affected and work resumed after an all-clear.

4 min read

QTS data center site in Georgia partially evacuated after shooting threat letterNetworks & Infrastructure
QTS data center site in Georgia partially evacuated after shooting threat letterdimitrisvetsikas1969 / pixabay

Why it matters

  • QTS paused work at its Fayetteville construction site on Nov. 18 after finding a written shooting threat.
  • Police received the threat report just before 1 p.m. local time on Wednesday, Nov. 19.
  • Buildings three and four were evacuated; police later granted an all-clear, and no customers were affected.
  • Project Excalibur plans 6.6 million sq ft across 16 buildings on 615 acres, with around 250MW of capacity.
  • The campus also faced a hoax bomb threat in July 2025.

The story

By Rebecca Stone

QTS partially evacuated its planned 250MW data center campus in Fayetteville, Georgia, after a shooting threat, and said no customers were affected.

What happened at the Fayetteville campus?

Fox and WSB were among the outlets that first reported the incident. The Fayetteville Police Department said it received a report of a shooting threat against the QTS Data Center on Wednesday, November 19.

Police were told just before 1 p.m. local time that a note threatening a shooting had been found on the campus. “Out of an abundance of caution, facility management made the decision to partially evacuate the campus while law enforcement personnel conducted their investigation,” police said.

According to The Citizen, buildings three and four were evacuated. After a search and investigation, police allowed staff to return to the site, although the investigation remains ongoing.

DCD reached out to QTS for comment. The company said:

“On November 18, out of an abundance of caution, work was temporarily paused at our Fayetteville construction site after a written threat was discovered. Law enforcement responded, the affected construction areas were evacuated as a precaution, and the site has since received the all-clear. There was no impact to customers, and construction resumed today.”

The accounts identify two dates rather than one. QTS says it found the written threat on November 18; police say they received the threat report just before 1 p.m. on Wednesday, November 19. The interval between those events was not disclosed.

Police said the department takes all threats of violence seriously, will continue investigating the circumstances surrounding the incident, and thanked data center personnel and the community for cooperating with the response.

Because the campus remains in development, QTS’s assurance that customers were unaffected is narrower than an outage statement for a live facility. No operating customer workloads or traffic volumes at the site were identified; the recorded disruption was to construction work.

How large is Project Excalibur?

QTS filed to develop Project Excalibur in 2022. The Fayetteville campus sits about 20 miles (32km) south of Atlanta. The plan calls for 6.6 million square feet (613,160 square metres) of data center space across 16 buildings on a 615-acre site, with around 250MW of total planned power capacity.

If floor area were divided evenly, 6.6 million square feet across 16 buildings implies an average of 412,500 square feet per building. That is arithmetic, not a building-by-building schedule; no such breakdown was provided.

The floor area, building count and 250MW figure remain development targets, not demonstrated operating capacity. The update did not say how much capacity or construction had entered service, and QTS disclosed no capital cost, customer commitments, utility-connection milestone or completion date.

Is this part of a wider threat pattern?

Threats against data centers are rare, the report said. The same Fayetteville campus also received a hoax bomb threat in July 2025.

In October 2021, a spate of bomb threats hit data centers across the United States, but authorities later determined that every one was a hoax. The threats said bombs would be detonated in facilities unless a ransom was paid, and the motive remained unclear.

Nothing in the account of the November letter establishes that it came from the same source, followed the 2021 ransom pattern or was another hoax. The current threat was described as a shooting warning, and no ransom demand was reported.

That distinction matters because a repeated hoax and an unresolved threat require different security responses, even when both produce an evacuation and lost construction time.

What happens next?

The immediate commercial milestone was therefore work restarting, not a service launch. Police’s investigation remains open, while the report does not identify an author or motive, or establish any connection to the July incident.

The public account describes a search, evacuation and all-clear, but gives no detail on post-incident security changes, including access controls or police presence. The campus’s longer-term operating procedures therefore remain unstated.

QTS gave no revised rollout date or additional investment figure, so there is no evidence to claim either a material project delay or an acceleration. The brief pause did not become a customer outage, according to the company, but the account does not quantify its financial cost.

The next concrete checkpoint is the police finding and any QTS disclosure of schedule impact; without both, the incident’s demonstrated commercial effect remains a short construction pause rather than a service disruption.

Also reported

Share this article:

« PreviousNext »

More from Rebecca Stone

Rebecca Stone

Show full bio

Correspondent covering technology and product news in Carrier business, 5G and 6G, fiber and broadband at Telecom Gazette.

560 articles