Nebius signs $12bn in Q3 AI contracts, fully covering capex
Nebius signed $12bn of Q3 contracts with prepayments covering all capex, cut payback to 1 year 7 months, and posted revenue of $980.8m, up 571 percent.
Networks & InfrastructureWhy it matters
- Nebius signed $12 billion of contracts in Q3 2026, with prepayments covering 100 percent of capex.
- Group revenue was $980.8 million, up 571 percent year on year; net loss narrowed to $37.5 million.
- Payback period shortened to 1 year 7 months, from 1 year 10 months in Q2.
- 2027 capex is expected at $40-45 billion; shares fell 18.48 percent.
- Microsoft's Vineland data center faced power delays; some capacity shifted to 2027.
The story
Nebius signed $12 billion of AI infrastructure contracts in the third quarter of 2026, with customer prepayments covering 100 percent of the capital expenditure needed to bring that capacity online, CEO Arkady Volozh said on today's earnings call.
The shift is stark when set against the prior quarter. In Q2, prepayments covered between 50 and 60 percent of capex requirements. Now customers pay the full cost of data centers, hardware and networking equipment upfront.
"As a result, payback in Q3 shortened to one year and seven months from one year and ten months a quarter earlier," Volozh said. "Our customers are paying more, they pay earlier, and they are committing for longer, and we are getting our capital back faster."
Who pays for the AI build-out?
Volozh opened the call by confronting the volatility that has shaken the AI infrastructure market in recent weeks. He framed the sector's central anxiety in two questions.
"Two questions are being asked of our whole industry: How fast can AI build-out happen, and who will pay for it? These are important questions," he said. "The demand for AI is real and substantial. Everything else, like building the capacity and financing it, is just a task. Tasks can be hard, but they can all be solved."
The prepayment structure is one answer. The other is debt. CFO Maria del Dado Alonso Sanchez pointed to the company's asset-backed financing framework, built on long-term customer agreements, which produced a $775 million facility signed in July.
"We have over $40 billion in such similar commitment revenue and see this as a repeatable framework," she said. She added that Nebius will flex between the two funding channels depending on conditions: if capital market terms are unattractive, the company allocates more capacity to long-term contracts; if debt is cheap, it will be "very opportunistic" and shift allocations accordingly.
Nebius expects full-year prepayments to total $10 billion.
What do the numbers show?
Group revenue reached $980.8 million in the quarter, up 571 percent year on year and up 68 percent quarter on quarter. Nebius AI Cloud delivered $973.8 million of that, a 643 percent increase, and roughly 99 percent of group revenue.
Net loss narrowed to $37.5 million, from $119.6 million a year earlier. The company expects pre-tax profitability in the fourth quarter of 2027.
Full-year revenue guidance sits at $3 billion to $3.2 billion — below earlier guidance because of data center delays. Annual recurring revenue is expected to exceed $7 billion by February, after which Nebius will stop reporting the metric. Dado said ARR is based on one month of the quarter and can add "choppiness" as new partnerships ramp.
Contracts signed in Q3 were priced at $25 million per megawatt.
Why was guidance cut?
Data center delays pushed a portion of this year's planned revenue into early 2027. "Building at this scale is hard, and delays are part of our industry right now. We are not immune," Volozh said.
The specific project is the Vineland data center being developed for Microsoft in New Jersey, where the problem is power generation. Nebius planned to bridge with temporary generation from DataOne while Bloom generators were deployed, but DataOne wound down its equipment faster than expected in late Q3. Volozh said Nebius is expediting the Bloom deployment but still faces a gap. He stressed that new tranches continue to be delivered to Microsoft through Q3, November and December, together with power delivery.
No capacity has been canceled. Some has shifted to 2027. Nebius's own sites remain on track or ahead of schedule.
The context matters for practitioners. Microsoft has reportedly been rethinking contracts with neocloud providers, increasing oversight of projects with Nebius, Iren and Nscale, and stepping away from those it deems risky. Iren disclosed a one-to-two-month delay after Microsoft requested a networking change. In the UK, Microsoft pulled out of Nscale's Loughton project after the grid could not provide a connection before the 2030s.
What comes next?
Quarterly capex was $7.3 billion, with full-year spending expected at $27 billion and contracted power reaching 5 GW by year-end. In 2027, Nebius anticipates capex of $40-45 billion to bring another gigawatt online, with 75 to 85 percent funded by prepayments and asset-backed financing. Despite the results, shares fell 18.48 percent at the time of writing.