Microsoft Starts Building Westgate Data Center North of Auckland

Construction began in September at Microsoft's Westgate site in New Zealand, likely expanding a cloud region powered by a 51.4MW geothermal PPA with Contact Energy signed in 2022.

3 min read

Microsoft begins work on Westgate data center in New ZealandNetworks & Infrastructure
Microsoft begins work on Westgate data center in New Zealandwal_172619 / pixabay

Why it matters

  • Construction at Microsoft's Westgate data center in New Zealand began in September 2025 per the company's project page.
  • The site is located at 7 Kakano Road with an entrance at 85 Rotu Drive, per Stop Data Centres Auckland.
  • Microsoft's New Zealand cloud region was announced May 2020, approved September 2020, and launched December 2024.
  • In 2022 Microsoft signed a 51.4MW ten-year geothermal PPA with Contact Energy for the Te Huka 3 power station.

The story

Microsoft began construction of its Westgate data center in New Zealand in September, according to the company's own project overview page, in what appears to be the first physical expansion of a cloud region that only went live in December 2024.

The disclosure is deliberately thin. Microsoft has not published capacity, IT load, or facility specifications for the site. What the company has confirmed is the construction sequence: "current and upcoming works include site establishment, piling, earthworks, excavation, concrete works, crane activity, and deliveries."

That phrasing places the project at the earliest stage of a multi-year build cycle. Piling and excavation typically precede any superstructure work by several months, so practitioners tracking New Zealand colocation and cloud capacity should not expect service availability in the near term.

Where exactly is the site?

The project page states the data center site is being accessed from Kakano Road. Local opposition group Stop Data Centres Auckland, in Facebook posts, has placed the project at 7 Kakano Road with an entrance at 85 Rotu Drive. That location sits in the Westgate area north-west of Auckland, near the city's established northern growth corridor.

For infrastructure planners, the interesting signal is the absence of detail. Microsoft rarely publishes per-site specifications, and this project page follows that pattern. DCD has contacted the company for further information, and any capacity figures will need to come from that follow-up or from regional consent filings.

How does this fit the New Zealand cloud region?

The timeline matters here. Microsoft first announced its New Zealand cloud region in May 2020 and received approval that September. The region then took more than four years to reach launch, going live in December 2024.

A new construction start eleven months after launch suggests the initial region footprint is already approaching its designed capacity, or that Microsoft is pre-positioning capacity for expected demand growth. The company has not said which, and the source offers no guidance.

The Westgate facility sits within that same commercial envelope. The region itself remains the anchor product; Westgate appears to be an expansion of it rather than a separate cloud location.

What powers the facility?

The energy picture is the most concrete part of this story. In 2022, Microsoft said the New Zealand cloud region would run on 100 percent renewable energy.

It then backed that commitment with a contract: a 51.4MW, ten-year geothermal power purchase agreement with Contact Energy, covering output from the Te Huka 3 power station near Taupo. To put that figure in context, 51.4MW is roughly the continuous draw of a small city district, and it is dedicated to a single cloud region and its supporting infrastructure.

Geothermal supply matters for practical reasons beyond the sustainability label. Unlike wind or solar, geothermal generation runs continuously, which suits data center baseload profiles and removes the need for matching renewable certificates to intermittent output.

For local energy watchers, a Westgate expansion raises the question of whether the existing 51.4MW agreement covers additional floor space or whether Microsoft will need to contract further generation. Microsoft has not addressed this, and the answer will likely surface in future PPA announcements rather than project documentation.

What comes next?

The immediate horizon is civil works. Site establishment, piling, and concrete activity will run through the coming months, with crane activity and deliveries following as structures rise. Any additional detail on capacity, timelines, or power contracting will depend on Microsoft's response to information requests, and the December 2024 region launch gives a rough template: from approval to operation, the original build took roughly four years.

Also reported

Share this article:

« PreviousNext »

More from Daniel Okafor

Daniel Okafor

Show full bio

Senior reporter covering regulation, policy and their impact on Carrier business, 5G and 6G, fiber and broadband at Telecom Gazette.

591 articles