ReuNION cable targets early 2029 between La Réunion and South Africa
The ReuNION consortium plans 16 fibre pairs from La Réunion to South Africa, with EU support for laying in 2027-2028 and readiness targeted for early 2029.
Networks & InfrastructureWhy it matters
- ReuNION's first phase uses 16 optical-fibre pairs between La Réunion and South Africa.
- Cable laying is expected in 2027 and 2028, with readiness scheduled for early 2029.
- A Singapore extension could raise the system from 16 to 24 fibre pairs.
- The first phase draws EU support through the Connecting Europe Facility and European Regional Development Fund.
- Possible future connections span Mauritius, Madagascar, Mayotte, India, Sri Lanka, Malaysia, Indonesia and the Maldives.
The story
ReuNION's first phase will connect La Réunion directly to South Africa with 16 pairs of optical fibres and is scheduled to be ready in early 2029.
The consortium brings together La Réunion Connectée, Orange, Reunicable and Telco OI. Its project, ReuNION—Reunion New Indian Ocean Network—aims to improve internet connectivity in the Indian Ocean.
The wider goal is to give Europe, Africa and Asia an alternative path for international data, making their connections more reliable and secure over the next 25 years. All four members are named, but the announcement assigns no lead construction role to any of them.
What will the two phases do?
- Phase one: A direct La Réunion–South Africa route with 16 pairs of optical fibres.
- Phase two: An extension to Singapore, creating a direct link between African and Asian digital networks. If built, the system would carry 24 pairs rather than 16.
That 25-year reliability and security objective is a design claim, not a measured service outcome: no traffic forecast, availability target or customer commitment appears in the disclosed details.
The phase-one route draws financial support from two EU funding instruments, the Connecting Europe Facility and the European Regional Development Fund. The announcement gives no support amount, award date or conditions, so the public contribution cannot be compared with the project's total cost.
Laying is expected in 2027 and 2028, with readiness scheduled for early 2029. The timetable is unusually concrete, but the announcement provides no separate commissioning period, contingency or detail on landing arrangements and procurement.
The Singapore extension does not have a disclosed construction or readiness date. Nor is it clear whether its cable would share the 2027-28 laying window or follow a separate schedule.
What does “open cable” mean?
ReuNION is designed as an “open cable,” the consortium says. Under that model, future investors can have a say in where extra connections are added. The structure preserves choices beyond the initial route; it also leaves the network's final shape dependent on commitments that have not yet been announced.
Possible connection points include Mauritius, Madagascar and Mayotte in the Indian Ocean, along with India, Sri Lanka, Malaysia, Indonesia and the Maldives. The list spans the Indian Ocean and Asia, but it remains a menu rather than a construction schedule.
No landing agreement or selection date is given for those locations. The announcement also does not explain how investor commitments would be allocated among the listed markets. “Open” describes the planned investment model, not completed construction.
What is proved, and what is not?
The consortium says the cable is designed to offer “a secure and neutral alternative to existing routes,” avoiding busy network connections and areas where data traffic may be disrupted. This is the central commercial and engineering pitch. It is not yet evidence that traffic will actually shift.
No throughput, transmission capacity per pair, route availability, subscriber count or commercial pricing is disclosed. No cable supplier, construction contractor, total capital cost or revenue model is named either. For a 25-year proposition, those omissions leave the investment case mostly in outline.
The move from 16 pairs in phase one to a possible 24 pairs after Singapore adds physical capacity, but pair count is not bandwidth. No transmission generation, optical standard or equipment plan is disclosed, so “more fibre” should not be treated as a throughput promise.
This is optical backbone infrastructure, not a radio-access rollout: no 3G, 4G or 5G generation applies to the project. The disclosed technical markers are the route, the number of optical-fibre pairs and the planned laying window.
Commercially, phase one has the stronger case: named partners, EU-backed support, fixed endpoints, a fibre count and dated delivery targets. Phase two has a destination, a higher pair count and the open investment framework, but it remains conditional. Investors, not adjectives, will decide whether the extension becomes financeable.
The next milestones are commitments from investors, landing-point decisions and confirmation of the Singapore extension. ReuNION must also convert its 2027-28 laying schedule into procurement and construction.
Until then, the 16-pair route is a dated plan rather than an operating result. The 2027-28 laying window is the next hard checkpoint, when the open investment model must turn into contracts and a finished route.