Equinix Plans $500M Dallas Data Center DA13-1
Equinix has filed plans for DA13-1, a $500 million, 372,445 sq ft data center in Dallas, adding to two earlier filings on West Mockingbird Lane totaling $836 million.
Networks & InfrastructureWhy it matters
- Equinix filed for DA13-1, a $500 million, 372,445 sq ft four-story data center in Dallas, with construction set for February 2027 to December 2029.
- Equinix filed for DA12-1 ($542.8 million) and DA12-2 ($293.7 million) at 1550 West Mockingbird Lane in November 2025.
- The DA13-1 site formerly hosted the Mockingbird Office Park, demolished around 2022.
- Equinix currently operates eight data centers in the Dallas area and one in Houston.
- The three planned projects total more than $1.3 billion in investment.
The story
Equinix has filed to build a $500 million data center in Dallas, Texas, its third major project on West Mockingbird Lane in just over a year. The filing signals sustained demand for colocation capacity in one of the largest data center markets in the United States.
An Equinix affiliate, DA12 LLC, submitted plans to the Texas Department of Licensing and Regulation for a project designated DA13-1. The planned facility at 1520 West Mockingbird Lane in Dallas County would rise four stories and span 372,445 square feet. Construction is scheduled to run from February 2027 to December 2029.
The site sits in an industrial area near Love Field Airport. It is currently vacant. The land formerly hosted the Mockingbird Office Park, a complex dating to the 1970s that was demolished around 2022.
Who owns the site?
Ownership has changed hands repeatedly. The property, formerly known as Oakbrook Plaza, was acquired by 2GR Equity and Legacy Capital in 2016, then passed to Center Court Partners in 2019.
DA12 LLC, the entity behind the DA13 filing, shares its listed address with Equinix. The company's Americas president, Arquelle Shaw, is the listed contact for the LLC.
What does this change for Dallas capacity?
The new project sits directly across the street from two earlier Equinix filings. In November 2025, the company filed to develop DA12-1 and DA12-2 at 1550 West Mockingbird Lane.
The three buildings together represent more than $1.3 billion in planned investment on a single corridor. The specifics:
- DA12-1: $542.8 million for a 372,515 sq ft (34,610 sqm), four-story facility. Work runs from February 2026 to October 2027.
- DA12-2: $293.7 million for another four-story building. Work runs from September 2027 to March 2028.
- DA13-1: $500 million for a 372,445 sq ft, four-story facility. Work runs from February 2027 to December 2029.
The DA12 site was previously occupied by the Taylor Publishing Company and Balfour Publishing. That building has been demolished.
The overlapping construction timelines indicate a phased campus buildout rather than isolated projects. DA12-2 and DA13-1 would be under construction simultaneously during parts of 2027.
How large is Equinix's Texas footprint?
Equinix currently lists eight data centers in the Dallas area. Across the rest of Texas, it operates one additional facility in Houston. The three new builds would expand that footprint substantially, assuming all filings proceed to completion.
Dallas has drawn heavy data center investment in recent years, driven by power availability, fiber connectivity and enterprise demand. Equinix's choice of a former office park site near Love Field Airport reflects a broader pattern: developers increasingly target demolished commercial properties in industrial zones rather than greenfield land closer to the urban core.
Filings with the Texas Department of Licensing and Regulation represent early-stage plans, not confirmed construction. Timelines can shift. The stated February 2027 start for DA13-1 leaves roughly two years for permitting, design and procurement before ground breaks.
If the schedules hold, Equinix would complete DA12-1 by October 2027, DA12-2 by March 2028 and DA13-1 by December 2029, delivering a three-building campus worth over $1.3 billion to North Texas by the end of the decade.