EdgeCore opens RN01 and tops out RN02 at Reno campus

EdgeCore has opened RN01 and topped out RN02 at its 56-acre Reno campus, part of a three-building plan for 216MW of IT capacity and nearly 1 million square feet.

4 min read

EdgeCore launches Reno data center, tops out second building on campusNetworks & Infrastructure
EdgeCore launches Reno data center, tops out second building on campusdimitrisvetsikas1969 / pixabay

Why it matters

  • RN01 launched and RN02 topped out on the same day at EdgeCore's 56-acre Reno Industrial Center campus.
  • Full build-out comprises three buildings, 216MW of IT capacity and nearly 1 million square feet, or 92,905 square metres.
  • The Reno campus broke ground in August 2023 after EdgeCore began considering a Reno project in 2018.
  • Partners Group acquired EdgeCore in 2022 and plans up to $1.2 billion for the acquisition and data center build-outs.
  • The Tahoe-Reno Industrial Center site uses closed-loop cooling to reduce water use.

The story

By Amara Osei

What has EdgeCore delivered in Reno?

EdgeCore Digital Infrastructure has launched RN01 and topped out RN02 at its 56-acre Reno, Nevada, campus, with full build-out planned for 216MW of IT capacity across three buildings. The company achieved both milestones on the same day, packing an opening and a construction high point into one announcement.

EdgeCore said on LinkedIn this week: “Yesterday, we celebrated the ribbon-cutting of our RN01 data center and the topping out of RN02 at our Reno Industrial Center campus.” It added: “Achieving both milestones on the same day underscores EdgeCore’s continued momentum and ability to deliver data center capacity with certainty.”

The first sentence records two physical events. The second is EdgeCore's assessment of its own delivery record, which is rather less measurable. RN01 is the building explicitly described as launched; EdgeCore gave no opening date, capacity allocation or customer details for RN02.

At full build-out, the Reno campus will contain three buildings totaling 216MW of IT capacity and nearly 1 million square feet, equivalent to 92,905 square metres. The 216MW figure describes the completed campus rather than either building's present load, and EdgeCore did not split the planned capacity among RN01, RN02 and the third building.

The site stands at the Tahoe-Reno Industrial Center and uses a closed-loop cooling system to reduce water use. The choice addresses one operating variable for a campus with a 216MW power target and a large floor area. EdgeCore did not quantify expected savings or compare the system with conventional cooling.

How long has EdgeCore been at it?

EdgeCore broke ground on the campus in August 2023, although it had considered a Reno project as far back as 2018. The company itself also launched in 2018, making the current three-building scheme a later stage in a long-running Reno effort rather than a fresh arrival.

Partners Group acquired EdgeCore in 2022 and plans to invest up to $1.2 billion to fund the acquisition and the build-out of existing and future data center sites. That figure describes an investment envelope across the wider portfolio, not a Reno-specific budget. No breakdown of spending, committed capital or drawdown schedule accompanied the campus announcement.

EdgeCore now has facilities in operation and under development in Silicon Valley, California; Phoenix, Arizona; Reno, Nevada; and at multiple sites in Virginia. Reno therefore joins a wider expansion spanning operating assets and projects still to come, a distinction that makes portfolio maps look busier than current capacity.

How much capacity is live?

RN01 is the only Reno building explicitly identified as launched. RN02's topping-out marks a different stage, and EdgeCore has not said when it will open or what capacity it will carry. The 216MW campus figure belongs to full build-out, so treating all of it as operating supply would overstate today's position.

That distinction does not make the milestones small. A launched data center and a topped-out building provide concrete evidence of delivery, even if the announcement offers no occupancy, customer, power-utilization or completion figures for RN02. In short, RN01 contributes operating capacity of an undisclosed amount, while RN02 represents a future step toward the full campus figure.

The closed-loop design offers a second operating proposition, although EdgeCore provides no savings percentage, consumption baseline or independent performance data. The same caution applies to the company's claim about delivering capacity with certainty. The announcement supplies milestones, not proof of certainty.

What comes next?

The next concrete checkpoint is RN02's opening, followed by delivery of the third building and the campus's remaining 216MW. EdgeCore has disclosed neither an RN02 completion date nor a timetable for full build-out, and the $1.2 billion Partners Group plan does not supply a Reno spending schedule.

The longer runway is visible in the dates: Reno planning dates to 2018, groundbreaking came in August 2023, and RN01 and RN02 reached their announced milestones this week. The open question is not whether EdgeCore has a Reno campus; it does. The next proof point will be RN02's opening and a disclosed timetable for the final building, which together determine when the campus's 216MW design becomes live capacity.

Also reported

Share this article:

« PreviousNext »

More from Amara Osei

Amara Osei

Show full bio

News editor covering technology and product news in Carrier business, 5G and 6G, fiber and broadband at Telecom Gazette.

591 articles