Principal Buys Switch Datacenters AMS2 in Woerden
Principal Asset Management buys Switch's AMS2 site in Woerden under a 20-year lease-back deal; refit targets 4.2MW with liquid cooling and a further 14MW possible.
Networks & InfrastructureWhy it matters
- Principal acquired Switch Datacenters AMS2 in Woerden (~5,500 sqm) with Switch signing a 20-year lease and retaining operations.
- Refurbishment will raise AMS2 capacity to approximately 4.2MW, with potential for a further 14MW.
- Principal European Data Centre Fund I raised €297 million ($333.4m) from 14 investors; AMS2 is its seventh asset.
- Switch operates AMS2, AMS3 and AMS4 in the Amsterdam region, with AMS5 planned and a new project in Warsaw.
- Principal manages more than $600 billion in assets under Principal Financial Group.
The story
Principal Asset Management has acquired Switch Datacenters' AMS2 facility in Woerden, roughly 40 km south-east of Amsterdam, with Switch signing a new 20-year lease and retaining full operational control of the carrier-neutral site.
The deal, announced this week, covers real estate and infrastructure assets only. The parties did not disclose financial terms. Principal made the acquisition on behalf of Principal European Data Centre Fund I, its closed manage-to-core vehicle. AMS2 becomes the seventh asset in that fund's portfolio.
The numbers frame the transaction. AMS2 offers approximately 5,500 sqm (59,200 sq ft) of lettable space. A refurbishment and expansion now under way will lift capacity to roughly 4.2MW of IT load. The site could take a further 14MW over the medium term, giving the location a potential end-state near 18MW.
Paul Lewis, managing director for European data centers at Principal Asset Management, said: "This acquisition further strengthens our exposure to one of Europe's most important data center markets and reflects our conviction in the long-term growth of digital infrastructure."
Lewis added: "AMS2 benefits from a high-quality location, a long-term tenant relationship, and a clear value-enhancement opportunity through the planned refurbishment program."
What does the structure mean for operators?
For practitioners, this is a sale-and-leaseback in all but name. Principal owns the bricks and shell. Switch Datacenters keeps the brand, the customers and the operations under a two-decade commitment, which gives the operator the certainty to invest in the upgrade without losing commercial control.
Cara Mascini, chief strategy officer at Switch Datacenters, said: "Increasing the sustainability of existing data centers like AMS2 is important to Switch Datacenters, in terms of economic lifetime, energy efficiency, and social and environmental impact."
Mascini added: "This agreement gives us long-term certainty to upgrade AMS2 for high-density workloads in a more sustainable manner while we continue to operate it under our own name and with our own customers."
The technical refit points squarely at high-density, AI-era workloads. Once complete, AMS2 will offer liquid direct-to-chip cooling plus hybrid air cooling, with closed-loop water-free technology addressing the water-usage scrutiny that hangs over Dutch data center permitting. The site will also feed waste heat into local heating networks, a move aligned with Dutch sustainability expectations.
AMS2 started life as a banking data center and disaster recovery site. Switch acquired it in 2014 and converted it to colocation, operating it ever since.
How does the fund stack up?
Principal European Data Centre Fund I raised €297 million ($333.4 million) from 14 investors and is now closed to new money. It first closed in February 2022 at €155 million ($175.8 million), beating its initial target, and reached final close in October 2023.
The fund's portfolio now spans:
- Barcelona, Spain
- The UK
- Amsterdam, the Netherlands
- Dublin, Ireland
- Frankfurt and Düsseldorf, Germany
Principal and Switch already have form together. In 2023 the investment firm announced plans to acquire and convert a logistics facility in Amsterdam into a 42MW data center for Switch.
Where does Switch go next?
Switch Datacenters, which is not affiliated with the US operator Switch Inc, runs three facilities in the Amsterdam region: AMS2, AMS3 and AMS4. It has a fourth Dutch site, AMS5, in planning and recently announced a project in Warsaw, Poland. Its original AMS1 facility went to Equinix in 2019. The De Groot Family Office holds a stake in Switch.
Principal Asset Management, the global investment solutions business of Principal Financial Group, manages more than $600 billion in assets.
With the lease locked for 20 years and the refurbishment targeting 4.2MW of liquid-cooled capacity, the Woerden site gives both parties a long runway — and the option of 14MW more when Amsterdam-area demand justifies it.