Networks & InfrastructureKazakhstanData CentersAI InfrastructureData Center Valley
Kazakhstan Lines Up 480MW Phase Two for its Data Center Valley
Boosteroid, Gaw Capital and Firebird AI sign preliminary deals for 480MW in Kazakhstan's Pavlodar region, part of a Data Center Valley plan targeting up to 1GW by 2029.
Networks & InfrastructureWhy it matters
- Boosteroid, Gaw Capital and Firebird AI signed preliminary agreements for 480MW of data center capacity in Kazakhstan, expandable to 620MW.
- Phase One of Data Center Valley totals 304MW across three facilities, with openings scheduled between Q2 and Q4 2027.
- The first 68MW data center is scheduled to open in Q2 2027; a 164MW Firebird AI facility follows in Q3 2027.
- Kazakhstan's Data Center Valley project targets up to 1GW in the Pavlodar region by 2029.
- Kazakhstan currently has just 19 data centers, according to DataCenterMap.
The story
Boosteroid, Gaw Capital and Firebird AI have signed preliminary agreements to build 480MW of data center capacity in Kazakhstan, the second phase of a national project targeting up to 1GW by 2029. The plans were revealed at a meeting between Prime Minister Olzhas Bektenov and Deputy Prime Minister and Minister of AI and Digital Development Zhaslan Madiyev.
The wider initiative, branded Data Center Valley, is described in official materials as a "technological and major economic project" for the Pavlodar region. Phase one is already under construction and adds three facilities totalling 304MW. Phase two, backed by the three new signatories, is designed for 480MW with headroom to expand to 620MW.
How far has Phase One construction progressed?
Kazakhtelecom chairman Bagdat Musin, in a progress report, said the first 68MW facility has moved beyond preparatory work into foundations, infrastructure and the administrative building. It is scheduled to open in the second quarter of 2027.
A second facility, a 164MW data center built for Firebird AI, is moving in parallel. Excavation is 70 percent complete, with phased expansion of computing capacity and energy infrastructure to follow. Completion and launch are set for the third quarter of 2027.
The third data center, at 72MW, is scheduled for commissioning in the fourth quarter of 2027. Taken together, Phase One would put 304MW into service within roughly 18 months of the first opening.
What comes after Phase Two?
According to a notice from the Prime Minister's office, Kazakhstan is negotiating with Aleria, Energy Capital Global and China Energy for an additional 240MW, expandable to 420MW. Talks for a third phase are also underway. If all options are exercised, the Pavlodar cluster could approach 1.4GW, well beyond the 1GW headline target.
Who are the new entrants?
Boosteroid is best known for cloud gaming. In November 2025 it formed a joint venture with DL Invest Group to build 12 hyperscale data centers in Europe, the first confirmed for Bielsko-Biała, Poland, in February 2025, with capacity of up to 300MW. Earlier this year the pair signed a $2.5bn infrastructure agreement with Argentum AI, under which Argentum AI will deploy GPU infrastructure inside their facilities.
Firebird AI is an AI cloud startup. In August it launched an Armenian AI data center, the largest such facility in the Caucasus, and expects 300MW of total capacity there by the end of 2027. The Armenian site runs on the Nvidia DSX platform and will be powered by more than 70,000 Nvidia Rubin and Blackwell GPUs.
Hong Kong-based Gaw Capital is a private equity firm focused on Asia-Pacific real estate, with holdings spanning residential development, offices, malls, hospitality, warehouses and data centers. Its role gives the Kazakh project an institutional capital backer rather than purely operational partners.
Why does this matter for a small market?
Kazakhstan is not an established data center market. DataCenterMap counts just 19 facilities in the country today. The Pavlodar project alone would multiply that installed base several times over in capacity terms, positioning a Central Asian state as a regional compute hub rather than a bystander.
Other players are testing the same thesis. Akashi is developing a 100MW data center in the country. Chinese IT firm Maase is exploring development there, and Veon broke ground on a facility in December 2025.
For operators and investors, the practical takeaway is timing. Phase One deliveries cluster across 2027, Phase Two contracts are still preliminary, and the additional 240MW under negotiation with Aleria, Energy Capital Global and China Energy remains subject to talks — meaning committed capacity and signed capacity should not be conflated when assessing the Kazakh pipeline.