Merlin pauses two Arasur data centers, plans €863mn storage retrofit
Merlin Properties has paused its Arasur 4 and 5 data centers in Álava after the Basque Government refused permits for partner Solaria's solar farms, freezing 48MW.
Networks & InfrastructureWhy it matters
- Merlin Properties paused work on its Arasur 4 and Arasur 5 buildings in Álava, Spain, freezing 48MW of planned capacity.
- The Basque Government's refusal to authorize Solaria's planned solar farms left both data centers without committed power.
- Merlin estimates an extra €863 million, mainly for battery energy storage, equal to 11.3 percent on planned investment, and expects to recoup about 35 percent.
- One Arasur building runs live at 24MW; a second was due live before the end of the year and a third next year.
- Spain's proposed data center royal decree, first put forward in late August, threatens the €1.6bn ($1.67bn) project.
The story
Merlin Properties has paused work on two data centers in Álava, Spain, freezing 48MW of planned capacity in the Bilbao area. The stop follows a power problem: the Basque Government has refused to authorize solar farms that energy partner Solaria had planned to feed the sites.
At the Arasur site, one building already runs live at 24MW. A second was due to go live before the end of the year and a third next year, and those latter two together total 48MW. Both now sit frozen.
Merlin chief executive Ismael Clemente confirmed that the company will not proceed until it has sufficient guarantees of electricity supply. The firm is already working with Solaria on alternatives, shifting that consumption to other parts of Spain with greater self-consumption capacity, where locally generated solar power can be used on site rather than exported.
Solaria was one of Merlin's energy partners in the region, and its renewable output was meant to cover part of the electricity needed to power both suspended buildings. Administrative problems have affected several of the company's solar projects, compromising a share of that planned supply.
The pause lands at a sensitive moment for regulation. The Spanish government first proposed a new regulatory framework for data centers in late August, and both Spain DC and individual operators have voiced skepticism since. A royal decree would force Merlin to retrofit its facilities, and the company has prepared a contingency plan for that eventuality. Its estimate carries a large price tag:
- €863 million — the additional cost Merlin calculates for adapting its facilities, mostly investment in battery energy storage systems (BESS).
- 11.3 percent — that extra sum on top of investments already included in the firm's plans.
- 35 percent — the share of the additional cost Merlin expects to recoup.
- €1.6bn ($1.67bn) — the total value of the project Clemente says could be jeopardized.
The company is working to safeguard the project's viability and anticipate the effects of the new rules, and it is also considering shifting part of its development capacity to Portugal and Madrid, alongside adding a second project in Aragón.
The supply crunch already shows in the design of the first building, which can accommodate up to 100MW of IT capacity. That headline figure runs fifty times the 2MW at which it would initially operate because of current electricity supply limits.
Energy supply has forced one retreat before. Merlin previously backed off plans for a campus in Andalusia for similar reasons, which makes Álava the second site where the grid, rather than demand, has set the pace.
The real estate firm first announced its move into data centers in 2021, partnering with Edged, the then-new venture from Aligned founder Jakob Carnemark. Since then it has raised more than $1bn for further development across a portfolio spanning two countries:
- Bilbao, Arasur, Madrid-Getafe, Barcelona and Lisbon are the current development locations across Spain and Portugal.
- Nebius is a confirmed customer; Meta is a rumored one.
Demand does not appear to be the binding constraint here. With customers already lined up, the pressure sits squarely on securing power, which turns a question of permits and self-consumption into a question of schedule.
The second Arasur building was due live before the end of the year, and that date now depends on electricity nobody has yet secured. Basque approvals, a workable alternative for Solaria's output and the final shape of the royal decree will decide whether the 48MW gets built in Álava or moves to Portugal, Madrid or Aragón.