Intersect Reserves 1.5GW of Heron Power Transformers for Data Centers
Intersect Power has reserved 1.5GW of Heron Power's solid-state transformers, with deliveries from 2028 as Alphabet's $4.75 billion acquisition fuels data center build-out.
Vendors & EquipmentWhy it matters
- Intersect has reserved 1.5GW of Heron Link solid-state transformers, with deliveries starting in 2028
- Heron Factory One in Morgan Hill, California is designed for 10,000 units annually, over 40GW of capacity, with mass production from late 2027
- Alphabet acquired Intersect in a deal reportedly worth $4.75 billion, closing in March
- Heron signed a deal with Vantage last month for more than 1GW of transformers and an LOI with Crusoe in June for the Stargate campus
- Intersect operates 2.2GW of solar PV and 2.4GWh of battery storage, mostly in Texas and California
The story
Intersect Power has reserved 1.5GW of solid-state medium-voltage transformers from US manufacturer Heron Power, with deliveries to the Alphabet-owned clean energy and data center developer expected to begin in 2028.
The manufacturing capacity agreement secures 1.5GW of Heron Link units for Intersect. Heron will build the transformers at Heron Factory One in Morgan Hill, California, a facility designed to produce up to 10,000 Heron Links per year — more than 40GW of manufacturing capacity. Mass production is expected to start in late 2027.
"This platform will accelerate our speed to power by improving energy delivery efficiency and is projected to decrease maintenance and downtime, while supporting manufacturing jobs in America," said Sheldon Kimber, founder and CEO of Intersect.
What does the deal change for Intersect?
For an operator racing to energize co-located data centers, the answer is queue position. Transformer lead times have become a bottleneck for grid-connected builds across the US, and reserving 1.5GW of dedicated manufacturing capacity four years ahead of first delivery gives Intersect a supply line independent of conventional transformer backlogs.
The agreement builds on an existing relationship. Intersect has worked with Heron as a technical and commercial collaborator for more than 18 months.
Heron describes the Heron Link as a modular megawatt power converter built on wide-bandgap semiconductors. The 5MW transformer is designed for high power density and ease of maintenance. The company claims the design offers greater reliability and lower costs for renewable energy storage and data center developers. Those claims remain vendor assertions until field deployments accumulate operating data.
A run of data center contracts
The Intersect deal is Heron's third with a data center-focused customer in just over a year. The sequence:
- Last June: a Letter of Intent with Crusoe to supply power converter technology for the Stargate data center campus in Texas.
- Last month: a deal with Vantage to deploy more than 1GW of transformers across the hyperscaler's data center portfolio.
- This week: the 1.5GW reservation with Intersect.
Heron Power was founded in 2024 by Drew Baglino, a former Tesla senior executive, and is based in Scotts Valley, California. Factory One in Morgan Hill has not yet reached mass production; the late-2027 target precedes the 2028 Intersect deliveries by a narrow margin, leaving little slack in the schedule.
Alphabet's power play behind the deal
Intersect brings its own scale to the agreement. The company operates a portfolio of 2.2GW of solar PV and 2.4GWh of battery storage in operation or construction, concentrated mostly in Texas and California.
Google first partnered with Intersect in 2024 to develop co-located renewable power and storage with new data centers across the US. Last December, Google's parent company Alphabet announced the acquisition of Intersect in a deal reportedly worth $4.75 billion, and closed the transaction in March.
In June, Intersect and Google began construction at the Meitner Energy Center in Gray and Roberts Counties, Texas, where the companies will colocate a data center alongside new energy generation. The Heron transformer capacity feeds directly into this build-out model, in which generation, storage and compute share a single site.
For Heron, the Intersect reservation adds a second gigawatt-scale commitment to an order book that now spans hyperscalers and clean energy developers alike. First deliveries under the agreement are expected in 2028, provided Factory One hits its late-2027 mass production milestone.
Also reported
Source: datacenterdynamics.com