FiveNines to steer 20MW AI data centre build near Casablanca

FiveNines Group will lead design and procurement for a 20MW AI data centre near Casablanca, the first phase of a 180MW AI factory Nexus Core Systems plans to deliver in Morocco next year.

3 min read

FiveNines joins Nexus project to build AI data centre in MoroccoNetworks & Infrastructure
FiveNines joins Nexus project to build AI data centre in MoroccoAI-generated

Why it matters

  • FiveNines Group will oversee development of a 20MW AI data centre on the outskirts of Casablanca, Morocco.
  • The facility is the first part of a 180MW AI factory Nexus Core Systems and partners aim to deliver sometime next year.
  • Nexus signed an MoU with Moroccan government agencies in April 2026 for the AI factory.
  • The 20MW site will use Nvidia's Vera Rubin NVL72 Cloud Partner Reference architecture.
  • FiveNines' mandate covers design, technical governance, procurement and preparation of the permit submission package.

The story

International data centre infrastructure firm FiveNines Group will manage delivery of a planned 20MW AI data centre on the outskirts of Casablanca, Morocco, partnering with AI infrastructure specialist Nexus Core Systems on the project.

The facility, revealed last week, forms part of a wider 180MW AI factory that Nexus and its international partners intend to deliver sometime next year. Nexus signed a memorandum of understanding with Moroccan government agencies in April 2026 to anchor the scheme.

The 20MW building will be purpose-designed for high-density AI computing. FiveNines says it will draw on the latest available semiconductors and Nvidia's Vera Rubin NVL72 Cloud Partner Reference architecture, a rack-scale platform aimed at large AI training and inference workloads.

What does the deal cover?

Under the partnership agreement, FiveNines leads the team handling:

  • design management
  • technical governance
  • consultant coordination
  • constructability
  • procurement strategy

The company will run the early-stage project process for the 20MW facility — briefing, feasibility, design strategy and concept design. The objective, according to FiveNines Group CEO Gerry Curran, is a coordinated design package fit for authority engagement and permit submission.

That detail matters. Permitting and authority approvals, not construction, typically set the pace for hyperscale projects entering a new market. Morocco has no established tier of AI-grade data centre capacity, so the design package will define how regulators and utilities engage with power and cooling requirements unfamiliar to local frameworks.

Who said what

Curran framed the assignment as a blend of imported expertise and local capability. "This project will bring together our international data centre expertise with Moroccan architects, engineers, technical advisers, and relevant authorities," he said in a statement.

He added that the project "further demonstrates the capability of FiveNines Group to undertake critical infrastructure projects of the highest standard alongside global industry leaders."

Nexus offered a shorter endorsement. Bastian Remmlinger, head of infrastructure at Nexus Core Systems, said FiveNines' team "has supported us well as we shape the design and delivery approach for the Morocco data centre."

Separating ambition from build

The commercial reality is that no steel has been committed. FiveNines' mandate covers early-stage coordination up to permit submission; construction contracts, power agreements and customer commitments for the 20MW facility remain undisclosed. The 180MW figure for the wider AI factory comes from the developer, and no anchor tenant or offtake arrangement has been named.

Still, the project carries weight for the North African market. A 20MW high-density AI facility would rank among the largest dedicated AI computing sites in the region, and the full 180MW factory — if delivered on the timetable Nexus has outlined — would position Morocco as a credible location for AI workloads seeking proximity to European networks and lower-cost power.

What does this change for telecom and cloud operators watching the region? It signals that AI compute capacity may emerge outside the traditional European core markets, with Casablanca's submarine cable connectivity and the April 2026 MoU providing the substrate for it.

The next checkpoint is the permit submission FiveNines is preparing the design package for. Nexus targets delivery of the 180MW AI factory sometime next year, a timeline that leaves little room for delay in Moroccan authority approvals.

Also reported

Share this article:

« Previous

More from James Calloway

James Calloway

Show full bio

Staff writer covering companies, deals and strategy in Carrier business, 5G and 6G, fiber and broadband at Telecom Gazette.

245 articles