Microsoft pulls out of Nscale's UK AI data center over power delays to 2030

Microsoft quits Nscale's planned UK AI data center after Essex power connection slips from end-2025 to at least 2030; Nscale seeks alternative power.

3 min read

Eurobites: Microsoft unplugs from Nscale data center project in UKNetworks & Infrastructure
Eurobites: Microsoft unplugs from Nscale data center project in UKhpgruesen / pixabay

Why it matters

  • Microsoft pulled out of Nscale's planned UK AI data center; the Essex site's power connection slipped from end-2025 to at least 2030.
  • Nscale and Microsoft continue joint data center projects in Norway, Portugal and the US.
  • VEON acquired Rubicon Wireless (Perfectum) in Uzbekistan for $207 million, adding 115MHz of spectrum and a Nokia-built 5G standalone network.
  • TIM appointed Poste Italiane' Mirko Mischiatti as chief enterprise officer and Claudio Ongaro as CTO after two executives confirmed departures at year-end.
  • Sky research found more than half of UK remote workers have turned off video cameras to keep connections stable.

The story

Microsoft has walked away from what was pitched as the UK's largest AI data center, after the Essex site was told its grid connection will not arrive until at least 2030 instead of the end of this year. Nscale, the UK-headquartered, Nvidia-backed developer, says the project will still proceed and, according to a BBC report, is exploring alternative power sources.

The withdrawal matters beyond one site. Power availability, not capital or silicon, is now the binding constraint on European AI infrastructure buildouts. A six-year slip on a connection originally promised for late 2025 is the kind of delay that moves hyperscaler money elsewhere. For practitioners, the signal is blunt: anchor tenants will not wait for grids.

Nscale and Microsoft continue to work together on data center projects in Norway, Portugal and the US. The commercial relationship survives. The UK site does not, at least in its original form. Nscale has previously positioned itself as the UK's AI hyperscaler hopeful, with Nokia named as a partner in earlier announcements.

Why did Microsoft leave?

The stated reason is power. The proposed site in southeastern England was originally scheduled to receive its power supply by the end of this year. That date has moved to at least 2030. Microsoft cited these delays when it pulled out. Nscale disputes none of the timeline. It simply argues the project is not dead.

A data center without a connection date is a stranded asset. Hyperscalers plan capacity years ahead. A 2030-plus energization makes the Essex site uncompetitive against Nscale's other markets with Microsoft, where power presumably exists or is contracted.

What else is moving in EMEA?

VEON buys Rubicon Wireless for $207 million. The Dubai-headquartered operator acquired the Uzbek business, which trades as Perfectum. The deal adds complementary spectrum and network assets to VEON's Beeline Uzbekistan operations: 115MHz across the 850MHz and 3,800MHz bands, plus equipment and infrastructure including a 5G standalone network built on Nokia gear. That low-band-plus-mid-band pairing gives Beeline both coverage depth and capacity for 5G.

TIM reshuffles its leadership. Telecom Italia appointed Mirko Mischiatti, from Poste Italiane, as chief enterprise officer and promoted Claudio Ongaro internally to chief technology officer. The changes follow confirmations that Elio Schiavo and Leonardo de Carvalho Capdeville will leave TIM at the end of the year. Poste Italiane, the state-owned postal group, launched its takeover bid for TIM in July. These appointments read as an early integration of state ownership into operational management.

Nokia's disposal problem persists. Nokia has found buyers for its fixed wireless access and private network assets, but its site implementation and microwave units remain without a clear outcome. The unsold units keep uncertainty alive for Nokia staff and customers alike.

Arelion grows Baltic traffic. The connectivity provider reports several new enterprise and wholesale customers onboarded on its multi-terabit Helsinki-Warsaw route. The route is part of a ring linking Sweden, Finland, Estonia, Latvia, Lithuania and Poland, with onward connections into neighboring countries. Baltic wholesale capacity demand appears firm.

Are UK remote workers really cursed by Wi-Fi?

Sky says yes, and it has a product to sell. Research from the UK pay-TV and broadband provider found that more than half of remote workers have turned off their camera during video calls to keep the connection stable. More than two in five say the phrase "Sorry, my Wi-Fi is playing up" has become routine in their working lives. Conveniently, Sky just launched a 1.6Gbit/s broadband package. Treat the numbers accordingly: real consumer friction, wrapped in vendor marketing.

What happens next?

Nscale says it will press on and find alternative power for Essex. If it succeeds, Microsoft could in principle return. If not, the UK's largest AI data center ambition will rest on sites elsewhere — and on a grid that delivers before 2030.

Also reported

Original: bbc.co.uk

Share this article:

« Previous

More from Daniel Okafor

Daniel Okafor

Show full bio

Senior reporter covering regulation, policy and their impact on Carrier business, 5G and 6G, fiber and broadband at Telecom Gazette.

372 articles