Kraft’s tentative Sutton data center campus would draw 900MW
A tentative 900MW Kraft Group campus in Sutton could bring $16bn of investment and lower tax bills, but power, workloads and a May 2027 approval remain unsettled.

Why it matters
- Sutton’s tentative campus would reach about 900MW at full build-out, with more than $16bn in developer-estimated private investment.
- Two 250,000-square-foot buildings at roughly 90MW each are planned for a 2029 launch, with expansion through 2033.
- Annual property tax is projected at $10.4m once fully assessed in 2031 and $27.8m at full build-out.
- The full-build tax projection nearly matches Sutton’s $32m FY2027 levy; average single-family bills could fall by $2,300 in FY2031 and $5,800 in FY2035.
- No formal application has been filed; parallel zoning, technical-review and community-benefits work culminates in a May 2027 town vote.
The story
By Rebecca Stone
The Kraft Group and Unified Global Packaging Group have outlined a tentative 900MW data center campus in Sutton, Massachusetts, backed by an estimated $16 billion in private investment, according to town manager Austin Cyganiewicz.
The memo to Sutton’s Select Board projects about $10.4 million in annual property tax once the campus property is fully assessed in 2031, rising to $27.8 million at full build-out. That later figure would almost match the town’s projected $32 million levy for FY2027, in a community of 9,357 residents at the 2020 census.
“Because the town raises only what its budget requires, the main effect would be lower tax bills,” Cyganiewicz added, “about $2,300 less for the average single-family home in FY2031 and about $5,800 less in FY2035.”
What would the Sutton campus contain?
The privately held, Robert Kraft-owned conglomerate would develop the campus with Sutton-based packaging firm Unified Global Packaging Group at Unified’s Parkway property, off Boston Road and Providence Road. The Kraft Group spans professional sports, manufacturing and real estate; Robert Kraft also owns the National Football League’s New England Patriots.
- Opening phase: Two buildings, each roughly 250,000 square feet (23,225 sqm), with about 90MW of power capacity apiece. The planned launch is 2029.
- Expansion: Two additional buildings each year over the next four years, taking the construction schedule through 2033.
- Full build-out: Around 900MW of capacity and more than $16 billion in private investment, based on developer estimates.
The two opening buildings would provide 180MW of the eventual 900MW capacity. Potential workloads were not disclosed, so neither an AI-related rationale nor the broader workload mix can be assessed. The memo also names no electricity supply agreement, customer commitment or equipment configuration.
What could happen to Sutton’s tax base?
Cyganiewicz put Sutton’s total assessed property value at $2.7 billion. Because the town raises only what its budget requires, the memo connects higher assessment to lower bills for existing homeowners. The calculations assume the campus receives approvals, is built and is assessed as projected.
The proposal remains tentative, with no formal application filed, so neither the construction timetable nor the projected tax savings is assured. The $16 billion investment figure also comes from the developer rather than an independently disclosed financing or construction-cost schedule.
What must be resolved before 2029?
Details on power, water and equipment have yet to be provided. Cyganiewicz said discussions are underway with the local regional grid operator to secure the necessary electricity, while reclaimed water would handle cooling. The memo does not identify that operator or quantify available capacity.
The approval path includes several tracks running in parallel: community-benefits discussions, zoning bylaws and technical review. Those processes are intended to culminate in a Sutton town meeting and vote in May 2027, making that vote the first defined public decision point.
At a Select Board meeting at Sutton Town Hall on November 10, 2026, residents could comment at the start of the session, although the meeting was not specifically a public hearing. Social-media comments afterward raised concerns about noise from an operating data center and the possibility of a local moratorium.
Massachusetts Governor Maura Healey’s executive order requires proposed data centers above 25MW to receive local community approval and requires developers to implement community-benefits agreements meeting state standards. The Sutton proposal falls within that state approval framework, bringing public scrutiny to both its infrastructure plans and potential community benefits.
The November 3 US midterms brought a wave of anti-data-center candidates into office, with AI data centers a key campaign issue. Voters also considered several data-center moratoria and other restrictive measures. Those national results were not a direct referendum on Sutton, but they form part of the political context in which the project must obtain local consent.
How firm is the 900MW plan?
The proposal’s scale is concrete; its delivery remains a set of assumptions. No formal application has been filed, workloads remain undisclosed, and the $16 billion estimate comes from the developer. The 2029 launch and 2033 full-build schedule are targets that depend on the May 2027 vote and subsequent infrastructure and permitting work.
The May 2027 town vote is the next hard checkpoint; without a formal application, secured grid capacity and detailed cooling and equipment plans, the 2029 launch remains a developer target rather than a committed operating date.