Harwood, North Dakota, Rejects Anti-Data-Center Measure as 40-Plus US Towns Say No
Harwood, ND rejected an anti-data-center measure 75.6% — the only US town to do so — clearing the path for Applied Digital's 1GW Polaris Forge 2 campus and $5B hyperscaler deal.
Networks & InfrastructureWhy it matters
- Harwood, North Dakota (pop. 845) rejected an anti-data-center measure with 75.6% of votes — the only US jurisdiction to do so amid 40+ such bills.
- Applied Digital's Polaris Forge 2 campus will reach 1GW; a 15-year, 200MW, $5 billion hyperscaler contract is already signed.
- The company has invested $100 million in local grid upgrades and $965,000 in community grants; the data center brings $1.65 million in property tax, six times Harwood's 2024 total.
- A gigawatt-scale Finland site was announced in October, with 100MW in phase one and initial power expected in 2028.
- CEO Wes Cummins targets six investment-grade hyperscale customers; three are secured, with CoreWeave a known US customer.
The story
Voters in Harwood, North Dakota — population 845 — rejected an anti-data-center ballot measure by 75.6 percent last week, making their town the only jurisdiction in the US to turn back such legislation alongside the 2026 midterm elections. The 75.6 percent amounted to just 325 people, but the signal was unambiguous in a year when more than 40 anti-data-center bills reached ballots nationwide and most passed.
The rejected measure would have required independent reviews and public hearings for data centers and other large industrial projects in Harwood. Applied Digital, the only data center operator building in the town, is constructing its Polaris Forge 2 campus just outside it — one of several sites the company is developing in North Dakota.
The commercial stakes are concrete. Polaris Forge 2 has an eventual capacity of 1GW. Last year Applied Digital signed a 15-year contract to supply 200MW to an unnamed investment-grade hyperscaler, a deal worth $5 billion. The same customer could take the remaining 800MW when the campus comes online.
What changed for the operator?
CEO Wes Cummins told DCD before the elections that the company has worked to "earn the right" to build in Harwood and across North Dakota. He frames local acceptance as an operating advantage competitors lack.
"Real estate is a very localized issue," Cummins said. "We focus a lot our time on the communities we operate in and trying to be responsive to any problems that arise. The other huge benefit for us is that we're the only data center company building in North Dakota, and the state has remained supportive. It's a unique situation to be in because we're not one of 400 or 500 companies trying to build something in a place like Texas."
The company's post-vote statement, emailed to DCD, cited local investments:
- $100 million in power grid upgrades in the area
- $965,000 in grants to local organizations
- $1.65 million in projected annual property tax revenue from the data center
That tax figure, noted by town mayor Blake Hankey in The Washington Post, is six times Harwood's total 2024 property tax take — a meaningful sum for a town of 845 residents. Against the $5 billion hyperscaler contract, however, the community spending is small by comparison.
Cummins draws a direct line between local conduct and expansion prospects. "What we do in these communities earns us the right to do it in again another community," he said. "If you work with the community the correct way, if you're transparent, and if you're attentive to the small things that people often overlook, you're going to do a good job, and you're going to create a great reputation for yourself."
Will the anti-data-center mood shift?
Cummins does not expect the political headwind to ease. "It's not going to go away," he said. "There's widespread agreement between members of both parties about the fact that they hate data centers, but I would say it's a high-level talking point and data centers are being made a scapegoat for a lot of other things."
That stance, he argued, will keep favoring permissive locations such as North Dakota while constraining operators elsewhere — a dynamic practitioners should read as a siting consideration rather than a national policy shift.
What comes next: Finland and the 'six Pokémon' strategy
Founded in 2021 as Applied Blockchain, the company also runs data centers in Alabama and Louisiana and is now pushing into Europe. In October it announced a gigawatt-scale development at an unnamed site in Finland, with initial power availability expected in 2028 and 100MW online in the first phase.
"It's paired with renewable energy, and is located in an area where a lot of other data centers are being built, so things like fiber are readily available," Cummins said. "This is the culmination of 18 months of looking at sites in Europe to find the right fit for us."
His target is six investment-grade hyperscale customers — his "Pokémon" — with three already secured and three to go. CoreWeave is a known US customer; the others remain undisclosed. A small European team is in place and expected to grow.
The Finland campus will reuse the US design process, with very large data hall footprints relative to power draw, 100 percent liquid cooling coverage and 80 percent air cooling availability. Cummins said customers are asking for more air cooling for specific inference deployments, and the large-format design covers a future return to 10kW per rack if power densities fall.
Also reported
Source: datacenterdynamics.com