CyrusOne and Kansai Electric Power topped out OSK1, a 48MW IT-capacity data center in Osaka, targeting first-phase operation by Q1 2028 as their 50:50 venture plans at least ¥1tn of investment.
Networks & InfrastructureWhy it matters
- OSK1 in Osaka is planned at 48MW of IT capacity across 11,560 square meters, or 124,430 square feet.
- Construction began in September 2024, and the first phase is scheduled to be operational by Q1 2028.
- CyrusOne and Kansai Electric formed a 50:50 data-center joint venture in May 2023.
- The partners plan at least ¥1 trillion ($7 billion) of investment over the next decade.
- Their business-scale target is 900MW, including 600MW of IT capacity.
The story
CyrusOne and Kansai Electric Power Company have topped out OSK1, a data center in Osaka, Japan, with 48MW of planned IT capacity across an 11,560-square-meter site.
OSK1 sits in Kansai and is the first CyrusOne KEP data center in Japan. Its 11,560-square-meter footprint equals 124,430 square feet.
The companies announced the milestone this week, while construction began in September 2024 and first-phase operation is scheduled by Q1 2028.
Topping-out confirms completion of the main steel frame, not readiness to host customers.
The announcement discloses no customer commitments, contracted IT load, power-supply terms or occupancy data for OSK1.
What does the topping-out milestone mean?
OSK1 has completed its main structural frame, the latest physical milestone before the remaining construction work.
The companies marked the event with a traditional Japanese Jōtōshiki ceremony, a ritual that recognizes the steel structure while wishing for safe and successful completion.
The ceremony featured gold and silver bolts driven into the final steel beam.
Takashi Mishima, co-CEO of CyrusOne KEP, said: “We are delighted to celebrate today’s topping out.”
His statement celebrates the ceremony itself; it does not indicate that construction, commissioning or customer occupancy has finished.
Suppliers still face the remaining construction program, while operators must wait for the announced first-phase opening by Q1 2028.
How large is the wider Japan commitment?
CyrusOne and Kansai Electric Power Company announced a 50:50 joint venture in May 2023 to develop new data centers across Japan.
- Investment: At least one trillion yen ($7 billion) over the next decade.
- Target scale: 900MW of business scale, including 600MW of IT capacity.
- Pipeline: Further project plans remain unshared; earlier ambitions included Tokyo and other major markets across Japan.
The stated $7 billion minimum averages roughly $700 million a year if spread evenly across ten years, although the partners have not disclosed project timing or allocations.
OSK1 converts the portfolio headline into a testable delivery: one named site, 48MW of planned IT capacity and a first-phase opening by Q1 2028.
The portfolio beyond OSK1 still lacks disclosed sites, capital allocations or commissioning dates, so it remains a development ambition rather than an operating footprint.
What does Kansai Electric bring?
Founded in 1951, Kansai Electric Power Company (KEPCO) owns and operates dozens of energy generation plants with combined capacity exceeding 35GW, or 35,000MW.
That installed base gives the data-center venture an established energy partner with generation assets already in operation.
KEPCO also owns ISP Optage, which announced in 2023 that it planned to build a new data center in Osaka, adding another network operator to the partner’s existing holdings.
The announcement gives no capacity, investment or commissioning date for the Optage proposal, and it does not quantify how either Optage or Kanden contributes to OSK1.
Kanden, another KEPCO subsidiary, is a real-estate development firm that adds property-development capability to the partner’s portfolio.
The disclosed ownership structure connects energy, network and real-estate assets, while OSK1’s 48MW target and Q1 2028 date offer the clearest near-term project markers.
What is new about CyrusOne’s Asian entry?
KKR-owned CyrusOne operates or develops more than 40 data centers across the United States and Europe, and OSK1 marks its first corporate expansion into Asia.
That footprint gives CyrusOne an established operating and development template, but the announcement names no tenants, contracted capacity or occupancy commitments for OSK1.
The 48MW figure therefore describes planned facility capacity, not occupied capacity, while the 900MW figure describes a future portfolio target.
The announcement also omits throughput, power-procurement terms and customer deployment schedules, leaving those commercial questions unresolved until CyrusOne releases more detail.
For telecom suppliers, headline megawatts alone do not establish the timing or scale of equipment orders.
OSK1 will not provide usable hosting capacity until its first phase opens in Q1 2028.
Which milestones come next?
Remaining construction comes first, with OSK1’s first phase scheduled to be operational by Q1 2028.
The next disclosure test is whether the partners name further Japanese sites and allocate investment against the 900MW portfolio target.
Earlier ambitions included Tokyo and other major Japanese markets, but the announcement provides no named site beyond OSK1.
OSK1’s Q1 2028 opening will provide the first hard test of whether CyrusOne and Kansai Electric can turn their minimum ¥1 trillion Japan plan into operating capacity.
Also reported
Source: datacenterdynamics.com
More from Daniel Okafor
Show full bio
Senior reporter covering regulation, policy and their impact on Carrier business, 5G and 6G, fiber and broadband at Telecom Gazette.
603 articles