Video & BroadcastBroadcast Positioning SystemAtsc 3 0Gps AlternativeTime Synchronization

Broadcast Towers Beat GPS Requirement at Dominion Substation Trial

Merkhet Solutions' 45-day BPS trial at a live Dominion Energy substation matched GPS accuracy and beat the utility's requirement by an order of magnitude, using ATSC 3.0 broadcast towers.

3 min read

BPS Trial at Dominion Energy Substation Proves SuccessfulVideo & Broadcast
BPS Trial at Dominion Energy Substation Proves Successfulds_30 / pixabay

Why it matters

  • 45-day BPS trial at a live Dominion Energy substation matched GPS timing accuracy, exceeding the utility's requirement by more than an order of magnitude.
  • Transmissions came from WHUT Washington (18.5 miles) and WNUV Baltimore (54.5 miles), both delivering UTC(NIST)-traceable time over ATSC 3.0.
  • Synchrophasor readings timed by BPS matched a GPS-timed substation on the same 500-kV line.
  • A 2025 NIST peer-reviewed paper concluded BPS is 'comparable to or better than GNSS' and a 'viable complementary PNT solution'.
  • Merkhet installed BPS receivers feeding IRIG-B into Dominion's digital fault recorder without interrupting operations.

The story

A 45-day trial at a live Dominion Energy substation found that Broadcast Positioning System (BPS) timing performed comparably to GPS, with accuracy more than an order of magnitude better than the utility's own requirement. Merkhet Solutions, which ran the trial, announced the results today.

BPS delivered GPS-independent time traceable to UTC (NIST) directly into the substation's fault-recording system. Two television stations carried the transmissions: WHUT in Washington, D.C., at a representative 18.5 miles (30 kilometers), and WNUV in Baltimore, deliberately stressed at 54.5 miles (88 kilometers). Both paths cleared the bar.

Why does a power utility care about TV towers?

Utilities need precision time to align grid measurements, locate transmission-line faults and reconstruct system events. At most substations, that time arrives solely from GPS — weak signals that can be jammed, spoofed or knocked around by solar storms. The trial asked whether BPS, riding on existing ATSC 3.0 broadcast towers, could stand in as a persistent alternative.

Dominion Energy's own fault-recording data supplied the verdict. Synchrophasor readings timed by BPS matched those from a GPS-timed substation at the other end of the same 500-kV line.

"Having an accurate and resilient source of time in the substation is important to Dominion Energy's core value of reliability," said Collin Gray, engineer, fault analysis at Dominion Energy. "We use time synchronization to analyze system events, align data across the grid, and provide transmission line fault locations to expedite restoration efforts."

Gray noted that the need keeps growing. "The importance of dependable time synchronization is only increasing with technologies like synchrophasors and IEC-61850 digital substations," he said. "Historically, GPS has been the sole source of this time signal. During this pilot project, Broadcast Positioning System (BPS) proved to be an accurate terrestrial alternative to GPS timing."

How was the trial run?

Merkhet Solutions installed BPS receivers and its own monitoring gear at the substation without interrupting operations. The receivers slotted into existing equipment and fed an IRIG-B signal straight into Dominion Energy's digital fault recorder. Both companies then collected and analyzed their measurements independently — a sensible precaution against grading your own homework.

The result carries a claim worth separating from the marketing. NIST, in a 2025 peer-reviewed paper presented at the Institute of Navigation International Technical Meeting, concluded that BPS time transfer is "comparable to or better than GNSS" and a "viable complementary PNT solution." That is the standards context: BPS is positioned as backup and complement, not a GPS replacement.

"Critical Infrastructure operators like Dominion Energy need a persistent alternate source of time they can rely on, and seeing it work at a live substation is an undeniable proof point," said Merkhet Solutions CEO Sam Matheny. "We're delighted that BPS exceeded Dominion Energy's requirement and demonstrated the viability of BPS using existing broadcast infrastructure and licensed spectrum."

The economics matter here. BPS needs no new towers and no new spectrum — it uses broadcast infrastructure and licenses broadcasters already hold. That is the difference between a pilot and a procurement line item.

Merkhet Solutions says more information is available on its website. With one live-substation proof point on record and NIST's backing in the literature, the next question is whether other utilities follow Dominion's lead on ATSC 3.0-derived timing.

Also reported

Share this article:

« Previous

More from Amara Osei

Amara Osei

Show full bio

News editor covering technology and product news in Carrier business, 5G and 6G, fiber and broadband at Telecom Gazette.

572 articles