Australian data center projects cancelled or paused after backlash
Quantum DC has paused a 1.2GW South Australian hyperscale proposal, while AirTrunk and Stockland have withdrawn major developments in Sydney’s Lane Cove and Cooks River after community opposition.
Networks & InfrastructureWhy it matters
- Quantum DC paused a 1.2GW hyperscale cloud and AI proposal at Tungkillo, South Australia.
- Stockland cancelled an AI data center within a $3.5 billion, 18.3-hectare Cooks River project.
- AirTrunk withdrew a 140MW Lane Cove West proposal; its SYD2 campus and approved adjoining development remain.
- Goodman dropped the 90MW Project Mars campus in September, citing policy, regulatory and community concerns.
- SCRAP claims hundreds mobilized at Cooks River, with further protests planned later this month.
The story
Quantum DC has paused planning approvals for its 1.2GW Tungkillo Compute and Energy Hub in South Australia, after AirTrunk and Stockland withdrew data center plans in Sydney’s Lane Cove and Cooks River following fierce community opposition.
At 1.2GW, Quantum’s cloud and AI proposal is nearly nine times the scale of AirTrunk’s withdrawn 140MW Lane Cove plan. The pause is a developer decision, not a reported government veto, and it leaves the project alive rather than cancelled.
Why did Cooks River lose its AI center?
Australian property firm Stockland has cancelled its planned AI data center at Cooks River, Sydney, and will proceed with the surrounding $3.5 billion logistics and commercial scheme across 18.3 hectares, or 45 acres. The joint venture with John Boyd Properties previously included the data center, on land formerly belonging to Kogarah Golf Club.
Opposition came through Stop the Cooks River AI Project, SCRAP, which claims to have mobilized hundreds against the data center and the wider scheme. Organizer and local resident Paddy Gibson said:
“This is an important victory for people power. Stockland’s backdown serves as yet another warning to political leaders at the federal and state level that are rolling out the red carpet for US tech bros. Local communities will not accept their obscene plans to make Australia the second home for power- and water-guzzling AI data centers.”
Stockland said its original concept offered several uses permitted under zoning, including data centers. The revised plan now focuses on logistics and mixed-use development.
Gibson welcomed the withdrawal but said the remaining works still threaten green space around Cooks River, which he described as a sanctuary for endangered native plants and animals. SCRAP plans further protests later this month.
Stockland is not exiting the sector: it has two Melbourne data center developments and one in Sydney that it announced this year. One local campaign has changed one Sydney plan, not the company’s Australian pipeline.
What happened at Lane Cove?
AirTrunk withdrew a proposed 140MW data center at Apollo Place and Mars Road in Lane Cove West. The APAC operator, owned by a Blackstone and Canada Pension Plan Investment Board consortium, described the site as unsuitable for the facilities its customers require.
AirTrunk said the withdrawal does not affect its operating SYD2 campus or an already approved adjoining Apollo Place development; together, they will form a larger integrated campus. The company has several Australian developments under way and will look for more feasible sites elsewhere in the country.
In September, Australian property firm Goodman Group dropped its separate 90MW Lane Cove West campus, Project Mars. It cited community feedback as a mitigating factor.
Local outlet In the Cove also reported the withdrawal of a Lane Cove project presented by the Lane Cove DC Alliance and backed by Australia’s Investment Delivery Authority.
The outlet’s investigation alleged that the alliance was not a registered business or company and identified Ford Land Company and Aurora Property Partnership as the actual developer. Aurora is related to Ausgrid, an Australian east-coast electricity provider.
What changed in the approval process?
Goodman said the policy and regulatory environment for large-scale data center development had evolved significantly. No single new federal rule is identified in the reported decisions; the immediate pressure comes from local planning, zoning and community objections. AirTrunk and Stockland withdrew projects, while Quantum paused approvals.
Why is Tungkillo on hold?
Quantum DC says it paused the project to undertake necessary engagement with the local community and South Australian government. Last month, it cancelled a drop-in meeting, claiming the event faced a credible bomb threat.
The planned 1.2GW hyperscale facility would house cloud and AI workloads, with on-site gas turbines for backup power and two new substations. It would also sit beside separately developed battery energy storage projects.
The data center footprint covers about 120 hectares, or 300 acres, within a 220-hectare, 550-acre site currently used for grazing. The remaining 100 hectares would stay in grazing use.
Quantum’s case for Tungkillo rested on what it calls a strategically significant position on South Australia’s transmission network, plus an existing high-pressure gas pipeline and fiber connection. The location case was concrete; community consent remained unresolved.
Quantum cancelled two community information sessions scheduled for later this month. It will replace them with a longer-term engagement program and says it wants reassurance that planning and assessment processes are being followed. It is also hearing a range of views on the proposal.
Quantum said it had misread the strength of feeling and that its first weeks of engagement created more questions than answers. It added:
“We are open to ideas that help shape this proposal, and nothing in the design is off the table. If the process shows that parts of the proposal need to change, they will change.”
Tungkillo is Quantum DC’s first project. Its long-term engagement program will determine whether the company can revise the design and return to the approval process.
Further protests are planned later this month, while Quantum has cancelled two information sessions in favour of longer engagement. AirTrunk will look for more feasible Australian sites, and Stockland’s other Sydney and Melbourne developments remain in progress. The near-term question is whether longer consultations can lead to revised approvals without another round of withdrawals.